Enterprise Risk & Business Continuity Framework
Add to watchlistA framework, policies and a single register for enterprise risk and business continuity, with a risk appetite approved by the board.
Budget (BAC)
Actual cost
96% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate8 January 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate9 March 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate3 June 2025Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate19 July 2026Closure · Current stageClosure · Current stage
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-07-19 | 2025-08-03 | +15 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-10-29 | 2025-11-24 | +26 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-02-08 | 2026-03-16 | +36 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-05-21 | 2026-07-07 | +47 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-08-31 | 2026-10-26 | +56 days | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Achieved | 1 | Approved |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
100%Awaiting acceptance
0%Not handed in
0%Deliverable flow
Display options
| Project plan & baseline030-D1 | 5% | CRT-030-01 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Dr. Amal F. Al-Sudairi | 2025-05-30 | V1 | 3 of 3 |
| Monitoring & reporting030-D2 | 5% | CRT-030-02 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa | Dr. Amal F. Al-Sudairi | 2025-07-19 | V1 | 3 of 3 |
| Current-state assessment030-D3 | 10% | CRT-030-03 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa | Dr. Amal F. Al-Sudairi | 2025-09-08 | V1 | 3 of 3 |
| Benchmarking030-D4 | 10% | CRT-030-04 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa | Dr. Amal F. Al-Sudairi | 2025-10-29 | V1 | 3 of 3 |
| Target model030-D5 | 15% | CRT-030-05 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa | Dr. Amal F. Al-Sudairi | 2025-12-19 | V1 | 3 of 3 |
| Roadmap030-D6 | 15% | CRT-030-06 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Dr. Amal F. Al-Sudairi | 2026-02-08 | V1 | 3 of 3 |
| Wave 1030-D7 | 15% | CRT-030-07 | Approved | Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa | Dr. Amal F. Al-Sudairi | 2026-03-31 | V1 | 3 of 3 |
| Wave 2030-D8 | 15% | CRT-030-08 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa | Dr. Amal F. Al-Sudairi | 2026-05-21 | V1 | 3 of 3 |
| Knowledge transfer030-D9 | 5% | CRT-030-09 | Approved | Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa | Dr. Amal F. Al-Sudairi | 2026-07-11 | V1 | 3 of 3 |
| Final report030-D10 | 5% | CRT-030-10 | Approved | Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa | Dr. Amal F. Al-Sudairi | 2026-08-31 | V1 | 3 of 3 |
| Total · 10 | 100% |