Project status card
28 October 2026 · 17 Jumada I 1448 AH
Arar Vocational Qualification Centre
PRJ-2026-034 · Qualification & Training Sector · External · WP-2025-034
- Progress
- 33% / 37%
- SPI · CPI
- 0.89 · 0.96
- Spend
- SAR 81.8M / SAR 238M
- Estimate at completion
- SAR 247.9M
Schedule
Planned to date 37%
Forecast finish: 2027-09-2827 Rabiʻ II 1449 AH · 28 days late
SPI0.89Schedule performance index · 0.89CPI0.96Cost performance index · 0.96Health dimensions
Last update: 2026-09-0220 Rabiʻ I 1448 AH · Update overdue
Deliverables
4 of 7 due deliverables accepted on time (57%)
Next milestones
- Build complete2027-03-0122 Ramadan 1448 AH
- Testing & acceptance complete2027-07-051 Safar 1449 AH
- Final handover2027-09-2726 Rabiʻ II 1449 AH
Top risks
- Municipality late bringing utilities and access roads to the site16
Open impediments
- Monthly progress reports incomplete · Overdue
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 238M: 0 on track and 0 red or critical. Weighted progress is 33% against 37% planned, spend SAR 81.8M, and EAC SAR 247.9M (SAR 9.9M over).
No project is more than a month behind baseline.