PRJ-2026-034At risk4ExecutionConstruction

Arar Vocational Qualification Centre

Add to watchlist

A training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Arar Vocational Qualification Centre

PRJ-2026-034 · Qualification & Training Sector · External · WP-2025-034

At risk4ExecutionProject manager: Eng. Ibrahim A. Al-Ghamdi · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦33%⁩ / ⁦37%⁩
SPI · CPI
0.89 · 0.96
Spend
SAR 81.8M / SAR 238M
Estimate at completion
SAR 247.9M

Schedule

⁦4%⁩ behind⁦33%⁩

Planned to date ⁦37%⁩

Forecast finish: 2027-09-2827 Rabiʻ II 1449 AH · 28 days late

SPI0.89Schedule performance index · 0.89CPI0.96Cost performance index · 0.96

Health dimensions

At risk

Last update: 2026-09-0220 Rabiʻ I 1448 AH · Update overdue

Deliverables

⁦4⁩ of ⁦7⁩ due deliverables accepted on time (⁦57%⁩)

Next milestones

  • Build complete2027-03-0122 Ramadan 1448 AH
  • Testing & acceptance complete2027-07-051 Safar 1449 AH
  • Final handover2027-09-2726 Rabiʻ II 1449 AH

Top risks

  • Municipality late bringing utilities and access roads to the site16

Open impediments

  • Monthly progress reports incomplete · Overdue

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 238M: 0 on track and 0 red or critical. Weighted progress is 33% against 37% planned, spend SAR 81.8M, and EAC SAR 247.9M (SAR 9.9M over).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Eng. Ibrahim A. Al-Ghamdi in MunjazInternal

Status: At risk ·Project page