Arar Vocational Qualification Centre
Add to watchlistA training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.
Budget (BAC)
Actual cost
34% of budget
Progress
Estimate at completion
SAR +9.9M
SPI · CPI
Forecast finish
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-12-15 | 2026-02-14 | +61 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-08-04 | +107 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-10-23 | 2027-03-01 | +129 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-04-28 | 2027-07-05 | +68 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-08-31 | 2027-09-27 | +27 days | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
33%Awaiting acceptance
12%Not handed in
55%Deliverable flow
Display options
| Project plan & baseline034-D1 | 3% | CRT-034-01 | Approved | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Yousef A. Al-Omari | 2025-10-14 | V1 | 3 of 3 |
| Monitoring & reporting034-D2 | 3% | CRT-034-02 | Approved | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa | Yousef A. Al-Omari | 2025-12-15 | V1 | 3 of 3 |
| Detailed design034-D3 | 7% | CRT-034-03 | Approved | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa | Yousef A. Al-Omari | 2026-02-16 | V1 | 3 of 3 |
| Permits & approvals034-D4 | 6% | CRT-034-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Yousef A. Al-Omari | 2026-04-19 | V1 | 3 of 3 |
| Site works & excavation034-D5 | 14% | CRT-034-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Yousef A. Al-Omari | 2026-06-20 | V1 | 3 of 3 |
| Structure034-D6 | 12% | — | Submitted | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Yousef A. Al-Omari | 2026-08-22 | V1 | 1 of 3 |
| Finishes034-D7 | 12% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa | Yousef A. Al-Omari | 2026-10-23 | V0 | 0 of 3 |
| Supply034-D8 | 10% | — | Draft | Eng. Ibrahim A. Al-GhamdiEng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionP-036i.alghamdi@sca.sa | Yousef A. Al-Omari | 2026-12-24 | V0 | 0 of 3 |
| Installation034-D9 | 10% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa | Yousef A. Al-Omari | 2027-02-25 | V0 | 0 of 3 |
| Testing & commissioning034-D10 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Yousef A. Al-Omari | 2027-04-28 | V0 | 0 of 3 |
| Provisional acceptance034-D11 | 7% | — | Draft | Yousef A. Al-OmariYousef A. Al-OmariDirector General, Partnerships & EventsP-016y.alomari@sca.sa | Yousef A. Al-Omari | 2027-06-30 | V0 | 0 of 3 |
| Final acceptance034-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Yousef A. Al-Omari | 2027-08-31 | V0 | 0 of 3 |
| Total · 12 | 100% |