Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-034At risk4ExecutionConstruction

Arar Vocational Qualification Centre

Add to watchlist

A training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-05-10⁩
Hijri
23 Dhuʻl-Qiʻdah 1447 AH
ApprovedCRT-034-03Detailed design

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-034
Project
Arar Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ibrahim A. Al-Ghamdi

1The deliverableAuto-filled

DeliverableAuto-filled
Detailed design
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Yousef A. Al-Omari
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦7%⁩
DueAuto-filled
⁦2026-02-16⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-034_2.1_v1.pdfV1Yousef A. Al-Omari⁦2025-12-24⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Yousef A. Al-Omari
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-025
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Yousef A. Al-OmariDirector General, Partnerships & EventsSubmitted—⁦2025-12-24⁩ 13:46
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-12-25⁩ 09:42
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Yousef A. Al-OmariApprovedInspected and accepted against the approved acceptance criteria.⁦2025-12-29⁩ 10:49
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-12-31⁩ 14:05
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-01-01⁩ 09:42

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-12-25⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2025-12-29⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-12-31⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-01-01⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Yousef A. Al-Omari on ⁦2025-12-24⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-12-25⁩ at ⁦09:42⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Yousef A. Al-Omari · Project owner

    Approved · ⁦2025-12-29⁩ at ⁦10:49⁩ · On behalf of Yousef A. Al-Omari (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-12-31⁩ at ⁦14:05⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-01-01⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-12-24⁩

    PRJ-2026-034_2.1_v1.pdf

    Yousef A. Al-Omari

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close