PRJ-2026-034At risk4ExecutionConstruction

Arar Vocational Qualification Centre

Add to watchlist

A training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.

Early warning: ⁦55%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 238M

Actual cost

SAR 81.8M

⁦34%⁩ of budget

Progress

⁦33%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 247.9M

SAR +9.9M

SPI · CPI

0.89Schedule performance index · 0.890.96Cost performance index · 0.96

Forecast finish

⁦2027-09-28⁩

28 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure29 June 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-12-08⁩
Hijri
7 Jumada II 1446 AH
ApprovedDMD-2026-034Arar Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-034
Project
Arar Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ibrahim A. Al-Ghamdi

1The proposalAuto-filled

TitleAuto-filled
Arar Vocational Qualification Centre
Proposed byAuto-filled
Eng. Ibrahim A. Al-Ghamdi
DepartmentAuto-filled
Professional Testing & Accreditation Department
Submitted onAuto-filled
⁦2024-12-08⁩
Proposal numberAuto-filled
DMD-2026-034

2Justification

A training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.

3Objectives

  1. Build capability and innovation in the sector
  2. A collaborative environment across the sector

Strategic objectives served

  • SO-2.1 — Build capability and innovation in the sector
  • SO-2.2 — A collaborative environment across the sector

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 238M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 171.4M
Supervision & consultingSAR 33.3M
Internal teamSAR 21.4M
Contingency reserve (5%)SAR 11.9M
TotalSAR 238M

6Initial risks

RiskLevelProposed response
Municipality late bringing utilities and access roads to the siteHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionSubmitted—⁦2024-12-08⁩ 09:36
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-12-09⁩ 13:16
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-12-12⁩ 14:23
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-12-15⁩ 09:30
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-12-16⁩ 09:12
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-12-19⁩ 11:44

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-12-09⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-12-12⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2024-12-15⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-12-16⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-12-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Ibrahim A. Al-Ghamdi on ⁦2024-12-08⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-12-09⁩ at ⁦13:16⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-12-12⁩ at ⁦14:23⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2024-12-15⁩ at ⁦09:30⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-12-16⁩ at ⁦09:12⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-12-19⁩ at ⁦11:44⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-12-29⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Ibrahim A. Al-Ghamdi

  2. V1Returned for edit⁦2024-12-08⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Ibrahim A. Al-Ghamdi