Arar Vocational Qualification Centre Subtask Last item under this branch 2027-09-27 33% Arar Vocational Qualification Centre Planned: 2025-07-06 → 2027-08-31 Forecast: 2025-07-06 → 2027-09-27 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-02-14 100% Management & governance Planned: 2025-07-06 → 2025-12-15 Actual: 2025-07-06 → 2026-02-14
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-20 100% Project plan & baseline Planned: 2025-07-06 → 2025-10-14 Actual: 2025-07-06 → 2025-11-20
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-14 100% Monitoring & reporting Planned: 2025-09-06 → 2025-12-15 Actual: 2025-09-30 → 2026-02-14
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-14 100% Project plan approved Planned: 2025-12-15 → 2025-12-15 Actual: 2026-02-14 → 2026-02-14 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-08-04 100% Design & permits Planned: 2025-11-08 → 2026-04-19 Actual: 2025-12-24 → 2026-08-04
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-10 100% Detailed design Planned: 2025-11-08 → 2026-02-16 Actual: 2025-12-24 → 2026-05-10
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-04 100% Permits & approvals Planned: 2026-01-09 → 2026-04-19 Actual: 2026-03-20 → 2026-08-04
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-04 100% Designs approved Planned: 2026-04-19 → 2026-04-19 Actual: 2026-08-04 → 2026-08-04 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-01 39% Civil works Planned: 2026-03-13 → 2026-10-23 Forecast: 2026-05-14 → 2027-03-01 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Site works & excavation Planned: 2026-03-13 → 2026-06-20 Actual: 2026-06-13 → 2026-10-26
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-18 18% Structure Planned: 2026-05-14 → 2026-08-22 Forecast: 2026-05-14 → 2027-01-18 Float: 0d Drag to change its duration +149
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-01 0% Finishes Planned: 2026-07-15 → 2026-10-23 Forecast: 2026-12-24 → 2027-03-01 Float: 0d Drag to change its dates +129
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-01 0% Build complete Planned: 2026-10-23 → 2026-10-23 Forecast: 2027-03-01 → 2027-03-01 Float: 210d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-07-05 0% MEP works Planned: 2026-09-16 → 2027-04-28 Forecast: 2027-02-04 → 2027-07-05 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-12 0% Supply Planned: 2026-09-16 → 2026-12-24 Forecast: 2027-02-04 → 2027-04-12 Float: 0d Drag to change its dates +109
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-24 0% Installation Planned: 2026-11-17 → 2027-02-25 Forecast: 2027-03-18 → 2027-05-24 Float: 0d Drag to change its dates +88
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-07-05 0% Testing & commissioning Planned: 2027-01-18 → 2027-04-28 Forecast: 2027-04-29 → 2027-07-05 Float: 0d Drag to change its dates +68
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-07-05 0% Testing & acceptance complete Planned: 2027-04-28 → 2027-04-28 Forecast: 2027-07-05 → 2027-07-05 Float: 84d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-09-27 0% Handover Planned: 2027-03-22 → 2027-08-31 Forecast: 2027-06-10 → 2027-09-27 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-08-16 0% Provisional acceptance Planned: 2027-03-22 → 2027-06-30 Forecast: 2027-06-10 → 2027-08-16 Float: 0d Drag to change its dates +47
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-27 0% Final acceptance Planned: 2027-05-23 → 2027-08-31 Forecast: 2027-07-22 → 2027-09-27 Float: 0d Drag to change its dates +27
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-09-27 0% Final handover Planned: 2027-08-31 → 2027-08-31 Forecast: 2027-09-27 → 2027-09-27 Float: 0d Drag to change its dates Final handover