Project status card
28 October 2026 · 17 Jumada I 1448 AH
Al-Khobar Branch — Rehabilitation & Extension
PRJ-2026-004 · Corporate Support Sector · Operational · WP-2024-004
- Progress
- 68% / 92%
- SPI · CPI
- 0.74 · 0.84
- Spend
- SAR 333.5M / SAR 412M
- Estimate at completion
- SAR 490.5M
Schedule
Planned to date 92%
Forecast finish: 2027-02-0326 Shaʻban 1448 AH · 126 days late
SPI0.74Schedule performance index · 0.74CPI0.84Cost performance index · 0.84Health dimensions
Last update: 2026-10-2110 Jumada I 1448 AH · Up to date
Deliverables
5 of 12 due deliverables accepted on time (42%)
Next milestones
- Testing & acceptance complete2027-02-169 Ramadan 1448 AH
- Final handover2027-03-0829 Ramadan 1448 AH
Top risks
- Main contractor cash-flow distress and unpaid subcontractors25
- Fire-fighting and evacuation systems failing Civil Defence requirements15
- Central HVAC failures during commissioning12
Open impediments
- Site labour stopped for 4 days over late wages · Escalated
- Leak in the underground water tanks during the water-tightness test · Open
- Incomplete bills of quantities attached to certificate 33 · Open
Decisions and changes waiting
- Direct payment to subcontractors at the Al-Khobar branch
Copilot summary
The scope holds 1 project with a budget of SAR 412M: 0 on track and 1 red or critical. Weighted progress is 68% against 92% planned, spend SAR 333.5M, and EAC SAR 490.5M (SAR 78.5M over).
1 project is more than a month behind baseline; the worst: Al-Khobar Branch — Rehabilitation & Extension (126 days).