PRJ-2026-004Critical4ExecutionConstruction

Al-Khobar Branch — Rehabilitation & Extension

Remove from watchlist

Rebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Al-Khobar Branch — Rehabilitation & Extension

PRJ-2026-004 · Corporate Support Sector · Operational · WP-2024-004

Critical4ExecutionProject manager: Eng. Waleed O. Al-Juhani · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦68%⁩ / ⁦92%⁩
SPI · CPI
0.74 · 0.84
Spend
SAR 333.5M / SAR 412M
Estimate at completion
SAR 490.5M

Schedule

⁦24%⁩ behind⁦68%⁩

Planned to date ⁦92%⁩

Forecast finish: 2027-02-0326 Shaʻban 1448 AH · 126 days late

SPI0.74Schedule performance index · 0.74CPI0.84Cost performance index · 0.84

Health dimensions

Critical

Last update: 2026-10-2110 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦12⁩ due deliverables accepted on time (⁦42%⁩)

Next milestones

  • Testing & acceptance complete2027-02-169 Ramadan 1448 AH
  • Final handover2027-03-0829 Ramadan 1448 AH

Top risks

  • Main contractor cash-flow distress and unpaid subcontractors25
  • Fire-fighting and evacuation systems failing Civil Defence requirements15
  • Central HVAC failures during commissioning12

Open impediments

  • Site labour stopped for 4 days over late wages · Escalated
  • Leak in the underground water tanks during the water-tightness test · Open
  • Incomplete bills of quantities attached to certificate 33 · Open

Decisions and changes waiting

  • Direct payment to subcontractors at the Al-Khobar branch

Copilot summary

The scope holds 1 project with a budget of SAR 412M: 0 on track and 1 red or critical. Weighted progress is 68% against 92% planned, spend SAR 333.5M, and EAC SAR 490.5M (SAR 78.5M over).

1 project is more than a month behind baseline; the worst: Al-Khobar Branch — Rehabilitation & Extension (126 days).

Saudi Contractors Authority · prepared by Eng. Waleed O. Al-Juhani in MunjazInternal

Status: Critical ·Project page