PRJ-2026-004Critical4ExecutionConstruction

Al-Khobar Branch — Rehabilitation & Extension

Remove from watchlist

Rebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.

Early warning: ⁦95%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 412M

Actual cost

SAR 333.5M

⁦81%⁩ of budget

Progress

⁦68%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 490.5M

SAR +78.5M

SPI · CPI

0.74Schedule performance index · 0.740.84Cost performance index · 0.84

Forecast finish

⁦2027-02-03⁩

126 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure13 July 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 November 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate14 January 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate20 June 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate13 July 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-06-18⁩
Hijri
29 Dhuʻl-Qiʻdah 1444 AH
ApprovedDMD-2026-004Al-Khobar Branch — Rehabilitation & Extension

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-004
Project
Al-Khobar Branch — Rehabilitation & Extension
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Waleed O. Al-Juhani

1The proposalAuto-filled

TitleAuto-filled
Al-Khobar Branch — Rehabilitation & Extension
Proposed byAuto-filled
Eng. Waleed O. Al-Juhani
DepartmentAuto-filled
Facilities Operations & Maintenance Department
Submitted onAuto-filled
⁦2023-06-18⁩
Proposal numberAuto-filled
DMD-2026-004

2Justification

Rebuilding the Eastern & Northern branch office and adding a new wing with 28 training and skills-test halls.

3Objectives

  1. Efficient, sustainable SCA facilities
  2. A better contractor experience and service quality

Strategic objectives served

  • SO-3.2 — Efficient, sustainable SCA facilities
  • SO-3.3 — A better contractor experience and service quality

4Expected benefits

KindBenefit
ProductivityTraining hours accommodated per year — target 43800 hours / year

5Cost & feasibility

Estimated cost

SAR 412M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 296.6M
Supervision & consultingSAR 57.7M
Internal teamSAR 37.1M
Contingency reserve (5%)SAR 20.6M
TotalSAR 412M

6Initial risks

RiskLevelProposed response
Main contractor cash-flow distress and unpaid subcontractorsHighTreated in the risk management plan
Fire-fighting and evacuation systems failing Civil Defence requirementsHighTreated in the risk management plan
Central HVAC failures during commissioningMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2023-06-18⁩ 12:45
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-06-20⁩ 10:55
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-06-25⁩ 11:02
4Portfolio manager reviewTechnical acceptanceEng. Mishari K. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-06-26⁩ 12:09
5Cost & funding reviewFinancial approvalApproval engineFinancePre-breach alert—⁦2023-06-29⁩ 08:00
6Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-07-02⁩ 12:21
7Project Approval CommitteeTechnical acceptanceApproval engineProject Approval CommitteePre-breach alert—⁦2023-07-06⁩ 08:00
8Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-07-09⁩ 14:23

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-06-20⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-06-25⁩

Portfolio manager review

Eng. Mishari K. Al-Otaibi

Approved⁦2023-06-26⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-07-02⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-07-09⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2023-06-18⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-06-20⁩ at ⁦10:55⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-06-25⁩ at ⁦11:02⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Mishari K. Al-Otaibi · Portfolio manager

    Approved · ⁦2023-06-26⁩ at ⁦12:09⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-07-02⁩ at ⁦12:21⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-07-09⁩ at ⁦14:23⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-07-09⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Waleed O. Al-Juhani

  2. V1Returned for edit⁦2023-06-18⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Waleed O. Al-Juhani