Al-Khobar Branch — Rehabilitation & Extension Subtask Last item under this branch 2027-03-08 68% Al-Khobar Branch — Rehabilitation & Extension Planned: 2024-01-14 → 2026-09-30 Forecast: 2024-01-14 → 2027-03-08 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2024-11-17 100% Management & governance Planned: 2024-01-14 → 2024-08-05 Actual: 2024-01-14 → 2024-11-17
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-07-21 100% Project plan & baseline Planned: 2024-01-14 → 2024-05-19 Actual: 2024-01-14 → 2024-07-21
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-11-17 100% Monitoring & reporting Planned: 2024-04-02 → 2024-08-05 Actual: 2024-05-11 → 2024-11-17
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-11-17 100% Project plan approved Planned: 2024-08-05 → 2024-08-05 Actual: 2024-11-17 → 2024-11-17 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-07-11 100% Design & permits Planned: 2024-06-19 → 2025-01-09 Actual: 2024-09-07 → 2025-07-11
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-15 100% Detailed design Planned: 2024-06-19 → 2024-10-23 Actual: 2024-09-07 → 2025-03-15
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-11 100% Permits & approvals Planned: 2024-09-06 → 2025-01-09 Actual: 2025-01-03 → 2025-07-11
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-11 100% Designs approved Planned: 2025-01-09 → 2025-01-09 Actual: 2025-07-11 → 2025-07-11 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-07-01 100% Civil works Planned: 2024-11-23 → 2025-09-02 Actual: 2025-05-01 → 2026-07-01
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-11-07 100% Site works & excavation Planned: 2024-11-23 → 2025-03-29 Actual: 2025-05-01 → 2025-11-07
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-05 100% Structure Planned: 2025-02-10 → 2025-06-16 Actual: 2025-08-28 → 2026-03-05
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-01 100% Finishes Planned: 2025-04-29 → 2025-09-02 Actual: 2025-12-24 → 2026-07-01
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-01 100% Build complete Planned: 2025-09-02 → 2025-09-02 Actual: 2026-07-01 → 2026-07-01 Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-02-16 40% MEP works Planned: 2025-07-17 → 2026-04-26 Forecast: 2025-10-04 → 2027-02-16 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Supply Planned: 2025-07-17 → 2025-11-20 Actual: 2026-04-21 → 2026-10-26
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-06 20% Installation Planned: 2025-10-04 → 2026-02-06 Forecast: 2025-10-04 → 2027-02-06 Float: 0d Drag to change its duration +365
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-16 0% Testing & commissioning Planned: 2025-12-21 → 2026-04-26 Forecast: 2027-01-31 → 2027-02-16 Float: 0d Drag to change its dates +296
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-16 0% Testing & acceptance complete Planned: 2026-04-26 → 2026-04-26 Forecast: 2027-02-16 → 2027-02-16 Float: 20d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-03-08 0% Handover Planned: 2026-03-10 → 2026-09-30 Forecast: 2027-02-10 → 2027-03-08 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-26 0% Provisional acceptance Planned: 2026-03-10 → 2026-07-13 Forecast: 2027-02-10 → 2027-02-26 Float: 0d Drag to change its dates +228
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-08 0% Final acceptance Planned: 2026-05-27 → 2026-09-30 Forecast: 2027-02-20 → 2027-03-08 Float: 0d Drag to change its dates +159
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-08 0% Final handover Planned: 2026-09-30 → 2026-09-30 Forecast: 2027-03-08 → 2027-03-08 Float: 0d Drag to change its dates Final handover