Project status card
28 October 2026 · 17 Jumada I 1448 AH
Institutional Performance Measurement & KPI Dashboard
PRJ-2026-012 · Strategy & Institutional Excellence Sector · Operational · WP-2025-012
- Progress
- 76% / 75%
- SPI · CPI
- 1.01 · 1.00
- Spend
- SAR 7.4M / SAR 9.8M
- Estimate at completion
- SAR 9.8M
Schedule
Planned to date 75%
Forecast finish: 2026-12-2415 Rajab 1448 AH · On time
SPI1.01Schedule performance index · 1.01CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-2716 Jumada I 1448 AH · Up to date
Deliverables
6 of 8 due deliverables accepted on time (75%)
Next milestones
- Testing & acceptance complete2027-01-0325 Rajab 1448 AH
- Final handover2027-01-2315 Shaʻban 1448 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 9.8M: 1 on track and 0 red or critical. Weighted progress is 76% against 75% planned, spend SAR 7.4M, and EAC SAR 9.8M (SAR 0M under).
No project is more than a month behind baseline.