PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Saudi Contractors Authority

Project charter

Institutional Performance Measurement & KPI Dashboard

APPROVEDV2Approved ⁦2025-09-05⁩

1Project identity

Required at this stage
Project name
Institutional Performance Measurement & KPI Dashboard
Project code
PRJ-2026-012
Project sponsor
Dr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.sa
Project manager
Tariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.sa
Project owner
Dr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.sa
Portfolio & programme
Institutional Excellence & Governance PortfolioInstitutional Excellence & Capability Programme
Type & methodology
Transformation · Agile
Current phase
4Execution

2Background & rationale

Required at this stage

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

3Objectives

Required at this stage
  1. 1A mature operating model and accountability

4Scope

Required at this stage

In scope

  • The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1As-is and to-be analysis
  2. 2Change management plan
  3. 3Adoption measures

6Deliverables

Required at this stage
1Project management plan⁦2025-09-26⁩
2Main deliverable — stage 1⁦2026-05-10⁩
3Main deliverable — final stage⁦2026-10-25⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-09-05⁩
  2. Contract signed⁦2025-11-23⁩
  3. 50% of works complete⁦2026-05-10⁩
  4. Provisional acceptance⁦2026-11-23⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦72.4%⁩7.1M
  • Supervision & consulting⁦13.3%⁩1.3M
  • Internal team⁦9.2%⁩900K
  • Contingency reserve (⁦5%⁩)⁦5.1%⁩500K
The owning sector’s approved budgetTotal9.8M

9Timeline

Required at this stage
Start
2025-09-0715 Rabiʻ I 1447 AH
Baseline finish
2026-12-3122 Rajab 1448 AH
Duration
⁦16⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3Target benefits within ⁦12⁩ months

15Governance structure

Required at this stage
  • Change Control BoardApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Board