PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project management plan

One plan bringing the schedule, deliverables, risks, communications, quality and benefits together from the project’s records, approved through the plan’s chain.

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Project management plan

Schedule, deliverables, risks, communications, quality and benefits

Form no.
SCA-PMO-F05
Template edition
2.0
Version
V2
Form date
⁦2025-10-02⁩
Hijri
10 Rabiʻ II 1447 AH
ApprovedPRJ-2026-012Institutional Performance Measurement & KPI Dashboard

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & KPI Dashboard
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1ScheduleAuto-filled

From the project schedule and its approved baseline.

Start

⁦2025-09-07⁩

Baseline finish

⁦2026-12-31⁩

Forecast finish

⁦2026-12-24⁩

SPI

1.01

MilestonePlannedForecastSlip
Project plan approved⁦2026-01-03⁩⁦2026-01-27⁩+24 days
Designs approved⁦2026-04-03⁩⁦2026-05-17⁩+44 days
Build complete⁦2026-07-03⁩⁦2026-09-03⁩+62 days
Testing & acceptance complete⁦2026-10-01⁩⁦2027-01-03⁩+94 days
Final handover⁦2026-12-31⁩⁦2027-01-23⁩+23 days

2DeliverablesAuto-filled

DeliverableWeightDueOwner
Project plan & baseline⁦5%⁩⁦2025-11-18⁩Tariq S. Al-Yami
Monitoring & reporting⁦5%⁩⁦2026-01-03⁩Dr. Amal F. Al-Sudairi
Current-state assessment⁦10%⁩⁦2026-02-17⁩Dr. Amal F. Al-Sudairi
Benchmarking⁦10%⁩⁦2026-04-03⁩Dr. Mohammed I. Al-Subaie
Target model⁦16%⁩⁦2026-05-19⁩Dr. Mohammed I. Al-Subaie
Roadmap⁦15%⁩⁦2026-07-03⁩Tariq S. Al-Yami
Wave 1⁦15%⁩⁦2026-08-17⁩Tariq S. Al-Yami
Wave 2⁦14%⁩⁦2026-10-01⁩Dr. Amal F. Al-Sudairi
Knowledge transfer⁦5%⁩⁦2026-11-16⁩Dr. Amal F. Al-Sudairi
Final report⁦5%⁩⁦2026-12-31⁩Dr. Mohammed I. Al-Subaie
Accepted with a certificate⁦76%⁩——

3RisksAuto-filled

CodeRiskScoreResponseOwner
No risks recorded

4CommunicationsAuto-filled

AudienceNeedFrequencyOwner
Project sponsorStatus and decisions neededMonthlyTariq S. Al-Yami
Project ownerDeliverable status and acceptance datesFortnightlyTariq S. Al-Yami
PMOData and indicator updatesWeeklyTariq S. Al-Yami
BeneficiariesWhat changes and whenAt each milestoneTariq S. Al-Yami
Team memberRoleAllocation
Tariq S. Al-YamiProject manager⁦60%⁩
Dr. Amal F. Al-SudairiProject sponsor⁦20%⁩

5QualityAuto-filled

  • Peer review of every deliverable before acceptance
  • Written acceptance criteria for every deliverable
  • A PMO audit at every gate

6BenefitsAuto-filled

BenefitBaselineTargetOwner
No benefits recorded

Approval logChain: Project management plan approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Performance & RiskSubmitted—⁦2025-10-02⁩ 13:40
2Methodology review — PMOMethodology reviewGhada A. Al-ShahraniPMO — analystApprovedComplete against the project management plan template.⁦2025-10-05⁩ 09:12
3Technical acceptance — project ownerTechnical acceptanceDr. Amal F. Al-SudairiProject ownerApproved—⁦2025-10-07⁩ 10:19
4Cash flow & financial commitmentFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-09⁩ 14:35
5Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-10-13⁩ 13:40

Signatures

Methodology review — PMO

Ghada A. Al-Shahrani

Approved⁦2025-10-05⁩

Technical acceptance — project owner

Dr. Amal F. Al-Sudairi

Approved⁦2025-10-07⁩

Cash flow & financial commitment

Munirah A. Al-Khalidi

Approved⁦2025-10-09⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2025-10-13⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F05 · version V2

Project management plan

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project management plan approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-10-02⁩

  1. Methodology review

    Methodology review — PMO

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-05⁩ at ⁦09:12⁩

    Complete against the project management plan template.

  2. Technical acceptance

    Technical acceptance — project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-10-07⁩ at ⁦10:19⁩

  3. Financial approval

    Cash flow & financial commitment

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-09⁩ at ⁦14:35⁩

  4. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-10-13⁩ at ⁦13:40⁩

Steps that do not apply to this record

  • Plan aligned with the contracts — the condition «Contract link?» does not hold

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-02⁩

    Approved with the baseline

    • Schedule and cost baseline approved

    Tariq S. Al-Yami

  2. V1Returned for edit⁦2025-09-18⁩

    First draft — returned to complete the quality plan

    • Plan from the methodology template

    Tariq S. Al-Yami