PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work9.5M⁦15⁩ elements
Unallocated contingency294KSAR 490K
Budget at completion9.8MPRJ-2026-012
Weighted progress⁦76%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project503⁦2025-09-07⁩⁦2027-01-23⁩⁦76%⁩9.517.45—
1
Phase142⁦2025-09-07⁩⁦2026-01-27⁩⁦100%⁩0.950.98—
1.1
WBS element88⁦2025-09-07⁩⁦2025-12-04⁩⁦100%⁩0.480.490 / 1
1.2
WBS element87⁦2025-11-01⁩⁦2026-01-27⁩⁦100%⁩0.480.491 / 2
2
Phase142⁦2025-12-26⁩⁦2026-05-17⁩⁦100%⁩1.901.96—
2.1
WBS element87⁦2025-12-26⁩⁦2026-03-23⁩⁦100%⁩0.950.981 / 1
2.2
WBS element88⁦2026-02-18⁩⁦2026-05-17⁩⁦100%⁩0.950.981 / 2
3
Phase142⁦2026-04-14⁩⁦2026-09-03⁩⁦100%⁩2.852.94—
3.1
WBS element88⁦2026-04-14⁩⁦2026-07-11⁩⁦100%⁩1.431.471 / 1
3.2
WBS element87⁦2026-06-08⁩⁦2026-09-03⁩⁦100%⁩1.431.471 / 2
4
Phase166⁦2026-07-21⁩⁦2027-01-03⁩⁦54%⁩2.851.57—
4.1
WBS element85⁦2026-08-02⁩⁦2026-10-26⁩⁦100%⁩1.431.471 / 1
4.2
WBS element166⁦2026-07-21⁩⁦2027-01-03⁩⁦7%⁩1.430.101 / 2
5
Phase26⁦2026-12-28⁩⁦2027-01-23⁩⁦0%⁩0.95——
5.1
WBS element16⁦2026-12-28⁩⁦2027-01-13⁩⁦0%⁩0.48—1 / 1
5.2
WBS element16⁦2027-01-07⁩⁦2027-01-23⁩⁦0%⁩0.48—1 / 1
Total⁦76%⁩9.517.45