Institutional Performance Measurement & KPI Dashboard Subtask Last item under this branch 2027-01-23 76% Institutional Performance Measurement & KPI Dashboard Planned: 2025-09-07 → 2026-12-31 Forecast: 2025-09-07 → 2027-01-23 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-01-27 100% Management & governance Planned: 2025-09-07 → 2026-01-03 Actual: 2025-09-07 → 2026-01-27
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-04 100% Project plan & baseline Planned: 2025-09-07 → 2025-11-18 Actual: 2025-09-07 → 2025-12-04
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-27 100% Monitoring & reporting Planned: 2025-10-22 → 2026-01-03 Actual: 2025-11-01 → 2026-01-27
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-27 100% Project plan approved Planned: 2026-01-03 → 2026-01-03 Actual: 2026-01-27 → 2026-01-27 Project plan approved
2 Diagnosis Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-05-17 100% Diagnosis Planned: 2025-12-07 → 2026-04-03 Actual: 2025-12-26 → 2026-05-17
2.1 Current-state assessment Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-23 100% Current-state assessment Planned: 2025-12-07 → 2026-02-17 Actual: 2025-12-26 → 2026-03-23
2.2 Benchmarking Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-17 100% Benchmarking Planned: 2026-01-21 → 2026-04-03 Actual: 2026-02-18 → 2026-05-17
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-17 100% Designs approved Planned: 2026-04-03 → 2026-04-03 Actual: 2026-05-17 → 2026-05-17 Designs approved
3 Design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-09-03 100% Design Planned: 2026-03-07 → 2026-07-03 Actual: 2026-04-14 → 2026-09-03
3.1 Target model Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-11 100% Target model Planned: 2026-03-07 → 2026-05-19 Actual: 2026-04-14 → 2026-07-11
3.2 Roadmap Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-03 100% Roadmap Planned: 2026-04-21 → 2026-07-03 Actual: 2026-06-08 → 2026-09-03
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-03 100% Build complete Planned: 2026-07-03 → 2026-07-03 Actual: 2026-09-03 → 2026-09-03 Build complete
4 Implementation Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-03 54% Implementation Planned: 2026-06-06 → 2026-10-01 Forecast: 2026-07-21 → 2027-01-03 Float: 0d
4.1 Wave 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Wave 1 Planned: 2026-06-06 → 2026-08-17 Actual: 2026-08-02 → 2026-10-26
4.2 Wave 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-03 7% Wave 2 Planned: 2026-07-21 → 2026-10-01 Forecast: 2026-07-21 → 2027-01-03 Float: 0d Drag to change its duration +94
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-03 0% Testing & acceptance complete Planned: 2026-10-01 → 2026-10-01 Forecast: 2027-01-03 → 2027-01-03 Float: 20d Drag to change its dates Testing & acceptance complete
5 Handover & knowledge transfer Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-23 0% Handover & knowledge transfer Planned: 2026-09-04 → 2026-12-31 Forecast: 2026-12-28 → 2027-01-23 Float: 0d
5.1 Knowledge transfer Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-13 0% Knowledge transfer Planned: 2026-09-04 → 2026-11-16 Forecast: 2026-12-28 → 2027-01-13 Float: 0d Drag to change its dates +58
5.2 Final report Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-23 0% Final report Planned: 2026-10-20 → 2026-12-31 Forecast: 2027-01-07 → 2027-01-23 Float: 0d Drag to change its dates +23
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-23 0% Final handover Planned: 2026-12-31 → 2026-12-31 Forecast: 2027-01-23 → 2027-01-23 Float: 0d Drag to change its dates Final handover