PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

3Achieved
0On track
1At risk
1Late
Average delay49 days
Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-07-03⁩Forecast / actual: ⁦2026-09-03⁩Delay: 62 daysG3 +62
Executive
Project plan approvedPlanned: ⁦2026-01-03⁩Forecast / actual: ⁦2026-01-27⁩Delay: 24 daysG1 +24
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-23⁩Delay: 23 daysG5 +23
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-01⁩Forecast / actual: ⁦2027-01-03⁩Delay: 94 daysG4 +94
Project
Designs approvedPlanned: ⁦2026-04-03⁩Forecast / actual: ⁦2026-05-17⁩Delay: 44 daysG2 +44

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-01-03⁩⁦2026-01-27⁩⁦+24⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-03⁩⁦2026-05-17⁩⁦+44⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-07-03⁩⁦2026-09-03⁩⁦+62⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saAchieved1Approved
Testing & acceptance completeMS-G4Regulatory⁦2026-10-01⁩⁦2027-01-03⁩⁦+94⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-23⁩⁦+23⁩ daysTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦76%⁩

Awaiting acceptance

⁦14%⁩

Not handed in

⁦10%⁩

Deliverable flow

Pick a stage to filter the register
⁦10⁩ results
Export CSV
Project plan & baseline012-D1⁦5%⁩CRT-012-01ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saDr. Amal F. Al-Sudairi⁦2025-11-18⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting012-D2⁦5%⁩CRT-012-02ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.saDr. Amal F. Al-Sudairi⁦2026-01-03⁩V1⁦3⁩ of ⁦3⁩
Current-state assessment012-D3⁦10%⁩CRT-012-03ApprovedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.saDr. Amal F. Al-Sudairi⁦2026-02-17⁩V1⁦3⁩ of ⁦3⁩
Benchmarking012-D4⁦10%⁩CRT-012-04ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saDr. Amal F. Al-Sudairi⁦2026-04-03⁩V1⁦3⁩ of ⁦3⁩
Target model012-D5⁦16%⁩CRT-012-05ApprovedDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saDr. Amal F. Al-Sudairi⁦2026-05-19⁩V1⁦3⁩ of ⁦3⁩
Roadmap012-D6⁦15%⁩CRT-012-06ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saDr. Amal F. Al-Sudairi⁦2026-07-03⁩V1⁦3⁩ of ⁦3⁩
Wave 1012-D7⁦15%⁩CRT-012-07ApprovedTariq S. Al-YamiTariq S. Al-YamiHead, Performance & RiskP-040t.alyami@sca.saDr. Amal F. Al-Sudairi⁦2026-08-17⁩V1⁦3⁩ of ⁦3⁩
Wave 2012-D8⁦14%⁩—SubmittedDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.saDr. Amal F. Al-Sudairi⁦2026-10-01⁩V1⁦1⁩ of ⁦3⁩
Knowledge transfer012-D9⁦5%⁩—DraftDr. Amal F. Al-SudairiDr. Amal F. Al-SudairiDirector General, Strategy & PerformanceP-015a.alsudairi@sca.saDr. Amal F. Al-Sudairi⁦2026-11-16⁩V0⁦0⁩ of ⁦3⁩
Final report012-D10⁦5%⁩—DraftDr. Mohammed I. Al-SubaieDr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence SectorP-009m.alsubaie@sca.saDr. Amal F. Al-Sudairi⁦2026-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 10⁦100%⁩
⁦1⁩–⁦10⁩ of ⁦10⁩