Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-03-23⁩
Hijri
4 Shawwal 1447 AH
ApprovedCRT-012-03Current-state assessment

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & KPI Dashboard
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The deliverableAuto-filled

DeliverableAuto-filled
Current-state assessment
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Dr. Amal F. Al-Sudairi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦10%⁩
DueAuto-filled
⁦2026-02-17⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-012_2.1_v1.pdfV1Dr. Amal F. Al-Sudairi⁦2025-12-26⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Dr. Amal F. Al-Sudairi
Accepted byAuto-filled
Dr. Mohammed I. Al-Subaie
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
—
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dr. Amal F. Al-SudairiDirector General, Strategy & PerformanceSubmitted—⁦2025-12-26⁩ 09:18
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-12-28⁩ 09:30
3Inspection & technical acceptance — ownerTechnical acceptanceDr. Mohammed I. Al-SubaieProject ownerOn behalf of Dr. Amal F. Al-SudairiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-12-30⁩ 10:37
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-01-01⁩ 12:57
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-01-04⁩ 13:34

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-12-28⁩

Inspection & technical acceptance — owner

Dr. Mohammed I. Al-Subaie

Approved⁦2025-12-30⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-01-01⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-01-04⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Dr. Amal F. Al-Sudairi on ⁦2025-12-26⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-12-28⁩ at ⁦09:30⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-12-30⁩ at ⁦10:37⁩ · On behalf of Dr. Amal F. Al-Sudairi (Dr. Mohammed I. Al-Subaie)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-01-01⁩ at ⁦12:57⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-01-04⁩ at ⁦13:34⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-12-26⁩

    PRJ-2026-012_2.1_v1.pdf

    Dr. Amal F. Al-Sudairi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close