Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
SCA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-09-05⁩
Hijri
13 Rabiʻ I 1447 AH
ApprovedPRJ-2026-012Institutional Performance Measurement & KPI Dashboard

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & KPI Dashboard
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1Objective

Background

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Project objectives

  1. A mature operating model and accountability

2Scope

In scope

  • The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.
  • As-is and to-be analysis
  • Change management plan

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-09-26⁩
Main deliverable — stage 1⁦2026-05-10⁩
Main deliverable — final stage⁦2026-10-25⁩
Final report⁦2026-12-31⁩
MilestoneDate
Charter approved⁦2025-09-05⁩
Contract signed⁦2025-11-23⁩
50% of works complete⁦2026-05-10⁩
Provisional acceptance⁦2026-11-23⁩
Closure⁦2026-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Dr. Mohammed I. Al-Subaie
Project ownerAuto-filled
Dr. Amal F. Al-Sudairi
Project managerAuto-filled
Tariq S. Al-Yami
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change Control BoardApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 7.1M
Supervision & consultingSAR 1.3M
Internal teamSAR 900K
Contingency reserve (5%)SAR 500K
Approved budgetSAR 9.8M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Performance & RiskSubmitted—⁦2025-08-27⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-08-30⁩ 12:30
3Project ownerTechnical acceptanceDr. Amal F. Al-SudairiProject ownerApproved—⁦2025-09-02⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-03⁩ 11:10
5Sponsor approvalTechnical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-09-05⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-08-30⁩

Project owner

Dr. Amal F. Al-Sudairi

Approved⁦2025-09-02⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-09-03⁩

Sponsor approval

Dr. Mohammed I. Al-Subaie

Approved⁦2025-09-05⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-08-27⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-08-30⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Dr. Amal F. Al-Sudairi · Project owner

    Approved · ⁦2025-09-02⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-03⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-09-05⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-05⁩

    Approved version

    • PMO comments addressed

    Tariq S. Al-Yami

  2. V1Returned for edit⁦2025-08-17⁩

    First draft

    • Returned to detail the budget

    Tariq S. Al-Yami

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close