PRJ-2026-012On track4ExecutionAgile

Institutional Performance Measurement & KPI Dashboard

Add to watchlist

The Authority’s strategic and operational KPIs — service times, contractor satisfaction, initiative delivery — on automated dashboards down to department level.

Budget (BAC)

SAR 9.8M

Actual cost

SAR 7.4M

⁦76%⁩ of budget

Progress

⁦76%⁩Awaiting acceptance ⁦14%⁩

Estimate at completion

SAR 9.8M

SPI · CPI

1.01Schedule performance index · 1.011.00Cost performance index · 1.00

Forecast finish

⁦2026-12-24⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate9 July 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate7 September 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate23 November 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 November 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-09-14⁩
Hijri
22 Rabiʻ I 1447 AH
ApprovedMTG-KO-012Kick-off — Institutional Performance Measurement & KPI Dashboard

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-012
Project
Institutional Performance Measurement & KPI Dashboard
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Strategy & Institutional Excellence Sector
Sponsor
Dr. Mohammed I. Al-Subaie
Project manager
Tariq S. Al-Yami

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Institutional Performance Measurement & KPI Dashboard
Date and timeAuto-filled
⁦2025-09-14⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Tariq S. Al-Yami

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Dr. Mohammed I. Al-SubaieHead, Strategy & Institutional Excellence Sector
Dr. Amal F. Al-SudairiDirector General, Strategy & Performance
Tariq S. Al-YamiHead, Performance & Risk
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Dr. Amal F. Al-SudairiDirector General, Strategy & Performance

2Roles

PersonRoleDuty
Dr. Mohammed I. Al-SubaieProject sponsorSponsors the project, decides escalations and material changes
Dr. Amal F. Al-SudairiProject ownerApproves the requirements and accepts the deliverables
Tariq S. Al-YamiProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Dr. Amal F. Al-SudairiProject sponsorDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedTariq S. Al-Yami⁦2026-01-03⁩Done
Designs approvedTariq S. Al-Yami⁦2026-04-03⁩Done
Build completeTariq S. Al-Yami⁦2026-07-03⁩Done
Testing & acceptance completeTariq S. Al-Yami⁦2026-10-01⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-11-23⁩
Start confirmed
Dr. Mohammed I. Al-Subaie · ⁦2025-09-15⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Tariq S. Al-YamiHead, Performance & RiskSubmitted—⁦2025-09-15⁩ 14:05
2Chair’s approval (sponsor)Technical acceptanceDr. Mohammed I. Al-SubaieProject sponsorApproved—⁦2025-09-16⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-17⁩ 12:39

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-09-17⁩

Chair’s approval (sponsor)

Dr. Mohammed I. Al-Subaie

Approved⁦2025-09-16⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Tariq S. Al-Yami on ⁦2025-09-15⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-17⁩ at ⁦12:39⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Dr. Mohammed I. Al-Subaie · Project sponsor

    Approved · ⁦2025-09-16⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-09-14⁩

    The minutes as taken

    Tariq S. Al-Yami

Only one version so far.