PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Qassim Vocational Qualification Centre

PRJ-2026-020 · Corporate Support Sector · Strategic · WP-2024-020

Off track4ExecutionProject manager: Eng. Ahmed Y. Asiri · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦44%⁩ / ⁦55%⁩
SPI · CPI
0.80 · 0.95
Spend
SAR 159.8M / SAR 345M
Estimate at completion
SAR 363.2M

Schedule

⁦11%⁩ behind⁦44%⁩

Planned to date ⁦55%⁩

Forecast finish: 2027-08-031 Rabiʻ I 1449 AH · 64 days late

SPI0.80Schedule performance index · 0.80CPI0.95Cost performance index · 0.95

Health dimensions

Off track

Last update: 2026-10-2413 Jumada I 1448 AH · Up to date

Deliverables

⁦4⁩ of ⁦9⁩ due deliverables accepted on time (⁦44%⁩)

Next milestones

  • Build complete2027-03-091 Shawwal 1448 AH
  • Testing & acceptance complete2027-06-0429 Dhuʻl-Hijjah 1448 AH
  • Final handover2027-08-0128 Safar 1449 AH

Top risks

  • Unforeseen ground conditions and groundwater at the foundations of axes 12 to 1620
  • Pile lengths exceeding contract quantities12

Open impediments

  • Excavation at axis 14 stopped by groundwater · In progress

Decisions and changes waiting

  • CR-2026-010 · Redesign the foundations of axes 12 to 16

Copilot summary

The scope holds 1 project with a budget of SAR 345M: 0 on track and 1 red or critical. Weighted progress is 44% against 55% planned, spend SAR 159.8M, and EAC SAR 363.2M (SAR 18.2M over).

1 project is more than a month behind baseline; the worst: Qassim Vocational Qualification Centre (64 days).

Saudi Contractors Authority · prepared by Eng. Ahmed Y. Asiri in MunjazInternal

Status: Off track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close