Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-020Off track4ExecutionConstruction

Qassim Vocational Qualification Centre

Remove from watchlist

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 345M

Actual cost

SAR 159.8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 363.2M

SAR +18.2M

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-11-05⁩
Hijri
21 Rabiʻ II 1445 AH
ApprovedDMD-2026-020Qassim Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
Qassim Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ahmed Y. Asiri

1The proposalAuto-filled

TitleAuto-filled
Qassim Vocational Qualification Centre
Proposed byAuto-filled
Eng. Ahmed Y. Asiri
DepartmentAuto-filled
Construction Projects Department
Submitted onAuto-filled
⁦2023-11-05⁩
Proposal numberAuto-filled
DMD-2026-020

2Justification

A training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.

3Objectives

  1. SCA services and programmes in every region

Strategic objectives served

  • SO-3.1 — SCA services and programmes in every region

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 345M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 248.4M
Supervision & consultingSAR 48.2M
Internal teamSAR 31.1M
Contingency reserve (5%)SAR 17.3M
TotalSAR 345M

6Initial risks

RiskLevelProposed response
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16HighTreated in the risk management plan
Pile lengths exceeding contract quantitiesMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction ProjectsSubmitted—⁦2023-11-05⁩ 10:31
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-11-07⁩ 14:41
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-11-08⁩ 09:48
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-11-12⁩ 10:55
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-11-14⁩ 10:07
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-11-19⁩ 12:09

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-11-07⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-11-08⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2023-11-12⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-11-14⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-11-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2023-11-05⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-11-07⁩ at ⁦14:41⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-11-08⁩ at ⁦09:48⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2023-11-12⁩ at ⁦10:55⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-11-14⁩ at ⁦10:07⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-11-19⁩ at ⁦12:09⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-11-26⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Ahmed Y. Asiri

  2. V1Returned for edit⁦2023-11-05⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Ahmed Y. Asiri

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close