Qassim Vocational Qualification Centre
Remove from watchlistA training and skills-test centre in Buraydah serving the Qassim region, with 30 halls and practical workshops.
Budget (BAC)
Actual cost
46% of budget
Progress
Estimate at completion
SAR +18.2M
SPI · CPI
Forecast finish
64 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure5 March 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-01-14 | 2025-05-14 | +120 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-07-06 | 2026-02-03 | +212 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-03-23 | 2027-03-09 | +351 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-12-09 | 2027-06-04 | +177 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-05-31 | 2027-08-01 | +62 days | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
44%Awaiting acceptance
12%Not handed in
44%Deliverable flow
Display options
| Project plan & baseline020-D1 | 3% | CRT-020-01 | Approved | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Eng. Bandar M. Al-Shammari | 2024-10-19 | V1 | 3 of 3 |
| Monitoring & reporting020-D2 | 3% | CRT-020-02 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2025-01-14 | V1 | 3 of 3 |
| Detailed design020-D3 | 6% | CRT-020-03 | Approved | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2025-04-10 | V1 | 3 of 3 |
| Permits & approvals020-D4 | 6% | CRT-020-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2025-07-06 | V1 | 3 of 3 |
| Site works & excavation020-D5 | 13% | CRT-020-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2025-10-01 | V1 | 3 of 3 |
| Structure020-D6 | 13% | CRT-020-06 | Approved | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Eng. Bandar M. Al-Shammari | 2025-12-27 | V1 | 3 of 3 |
| Finishes020-D7 | 12% | — | Submitted | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-03-23 | V1 | 1 of 3 |
| Supply020-D8 | 10% | — | Draft | Eng. Ahmed Y. AsiriEng. Ahmed Y. AsiriDirector, Construction ProjectsP-020a.asiri@sca.sa | Eng. Bandar M. Al-Shammari | 2026-06-18 | V0 | 0 of 3 |
| Installation020-D9 | 10% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2026-09-13 | V0 | 0 of 3 |
| Testing & commissioning020-D10 | 10% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2026-12-09 | V0 | 0 of 3 |
| Provisional acceptance020-D11 | 7% | — | Draft | Eng. Bandar M. Al-ShammariEng. Bandar M. Al-ShammariDirector General, Facilities & PremisesP-013b.alshammari@sca.sa | Eng. Bandar M. Al-Shammari | 2027-03-05 | V0 | 0 of 3 |
| Final acceptance020-D12 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziHead, Qualification & Training SectorP-010t.alanazi@sca.sa | Eng. Bandar M. Al-Shammari | 2027-05-31 | V0 | 0 of 3 |
| Total · 12 | 100% |