Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-021On track3PlanningConstruction

Asir Vocational Qualification Centre

Add to watchlist

A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

Budget (BAC)

SAR 520M

Actual cost

SAR 10.4M

⁦2%⁩ of budget

Progress

⁦2%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 520M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2028-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution12 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate4 February 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 April 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate12 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2025-09-07⁩
Hijri
15 Rabiʻ I 1447 AH
ApprovedDMD-2026-021Asir Vocational Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-021
Project
Asir Vocational Qualification Centre
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Ibrahim A. Al-Ghamdi

1The proposalAuto-filled

TitleAuto-filled
Asir Vocational Qualification Centre
Proposed byAuto-filled
Eng. Ibrahim A. Al-Ghamdi
DepartmentAuto-filled
Construction Projects Department
Submitted onAuto-filled
⁦2025-09-07⁩
Proposal numberAuto-filled
DMD-2026-021

2Justification

A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.

3Objectives

  1. SCA services and programmes in every region

Strategic objectives served

  • SO-3.1 — SCA services and programmes in every region

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 520M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 374.4M
Supervision & consultingSAR 72.8M
Internal teamSAR 46.8M
Contingency reserve (5%)SAR 26M
TotalSAR 520M

6Initial risks

RiskLevelProposed response
Tender prices 18% above the engineer’s estimateHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ibrahim A. Al-GhamdiDirector, Engineering SupervisionSubmitted—⁦2025-09-07⁩ 11:38
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2025-09-08⁩ 09:18
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-09-10⁩ 10:25
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2025-09-15⁩ 11:32
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-09-18⁩ 11:14
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2025-09-24⁩ 13:46

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2025-09-08⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2025-09-10⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2025-09-15⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2025-09-18⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2025-09-24⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Ibrahim A. Al-Ghamdi on ⁦2025-09-07⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2025-09-08⁩ at ⁦09:18⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-09-10⁩ at ⁦10:25⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2025-09-15⁩ at ⁦11:32⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-09-18⁩ at ⁦11:14⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2025-09-24⁩ at ⁦13:46⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-09-28⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Ibrahim A. Al-Ghamdi

  2. V1Returned for edit⁦2025-09-07⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Ibrahim A. Al-Ghamdi

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close