Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- SCA-PMO-F01
- Template edition
- 2.1
- Version
- V2
- Form date
- 2025-09-07
- Hijri
- 15 Rabiʻ I 1447 AH
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-021
- Project
- Asir Vocational Qualification Centre
- Portfolio
- Headquarters & Regional Centres Portfolio
- Sector
- Corporate Support Sector
- Sponsor
- Eng. Turki A. Al-Anazi
- Project manager
- Eng. Ibrahim A. Al-Ghamdi
1The proposalAuto-filled
- TitleAuto-filled
- Asir Vocational Qualification Centre
- Proposed byAuto-filled
- Eng. Ibrahim A. Al-Ghamdi
- DepartmentAuto-filled
- Construction Projects Department
- Submitted onAuto-filled
- 2025-09-07
- Proposal numberAuto-filled
- DMD-2026-021
2Justification
A 120,000 m² regional training and skills-test centre in Abha serving Asir, Jazan, Najran and Al-Baha.
3Objectives
- SCA services and programmes in every region
Strategic objectives served
- SO-3.1 — SCA services and programmes in every region
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SAR 520M
Funding
The owning sector’s approved budget
| Cost line | Amount |
|---|---|
| Main contract | SAR 374.4M |
| Supervision & consulting | SAR 72.8M |
| Internal team | SAR 46.8M |
| Contingency reserve (5%) | SAR 26M |
| Total | SAR 520M |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| Tender prices 18% above the engineer’s estimate | High | Treated in the risk management plan |
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Eng. Ibrahim A. Al-GhamdiDirector, Engineering Supervision | Submitted | — | 2025-09-07 11:38 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Reem K. Al-DosariThe requester’s line manager | Approved | — | 2025-09-08 09:18 |
| 3 | PMO review | Methodology review | Ghada A. Al-ShahraniPMO — analyst | Approved | — | 2025-09-10 10:25 |
| 4 | Portfolio manager review | Technical acceptance | Eng. Bandar M. Al-ShammariPortfolio manager | Approved | Consistent with the portfolio plan and its priorities. | 2025-09-15 11:32 |
| 5 | Cost & funding review | Financial approval | Munirah A. Al-KhalidiFinance | Approved | — | 2025-09-18 11:14 |
| 6 | Project Approval Committee | Technical acceptance | Dr. Noura M. Al-OtaibiProject Approval Committee | Approved | — | 2025-09-24 13:46 |
Signatures
Line manager endorsement
Eng. Reem K. Al-Dosari
Approved2025-09-08
PMO review
Ghada A. Al-Shahrani
Approved2025-09-10
Portfolio manager review
Eng. Bandar M. Al-Shammari
Approved2025-09-15
Cost & funding review
Munirah A. Al-Khalidi
Approved2025-09-18
Project Approval Committee
Dr. Noura M. Al-Otaibi
Approved2025-09-24