PRJ-2026-029On track3PlanningWaterfall

SCA Academy — Learning Platform & Professional Tracks

Add to watchlist

A learning management platform for qualification programmes and accredited professional tracks for sector workers, with accredited training partners.

Budget (BAC)

SAR 7.5M

Actual cost

SAR 300K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 7.5M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2026-02-23⁩
Hijri
6 Ramadan 1447 AH
ApprovedDMD-2026-006SCA Academy — learning platform

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-029
Project
SCA Academy — Learning Platform & Professional Tracks
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Qualification & Training Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Ghada A. Al-Shahrani

1The proposalAuto-filled

TitleAuto-filled
SCA Academy — learning platform
Proposed byAuto-filled
Abdulmajeed R. Al-Dosari
DepartmentAuto-filled
General Directorate of Human Resources
Submitted onAuto-filled
⁦2026-02-23⁩
Proposal numberAuto-filled
DMD-2026-006

2Justification

The problem or need

Thousands of contractors and sector workers join the Academy every year with no single learning platform, and 42% of programmes run on separate sheets and files with no single trainee record.

Today

Scattered courses with no accredited professional tracks and no impact measurement.

3Objectives

  1. A learning platform for the SCA Academy serving 15,000 trainees a year with accredited professional tracks for contractors and sector workers, with an accredited academic partner.

Strategic objectives served

  • SO-4.4 — Leadership and human capital

4Expected benefits

KindBenefit
Productivity80% of leadership posts filled internally
Cost savingExternal training cost down SAR 2.4M a year

5Cost & feasibilityAuto-filled

Estimated cost

SAR 7.5M

Net present value

SAR 1.8M

Return on investment

⁦31%⁩

Payback

3.7 years

YearCapexOpexBenefit
2026SAR 4.5MSAR 0SAR 0
2027SAR 3MSAR 800KSAR 1.6M
2028SAR 0SAR 800KSAR 2.9M
2029SAR 0SAR 850KSAR 3.4M
2030SAR 0SAR 850KSAR 3.6M
2031SAR 0SAR 900KSAR 3.8M

6Initial risks

RiskLevelProposed response
Late participant nominationsMediumApproved quotas per sector and branch

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Abdulmajeed R. Al-DosariDirector General, Human ResourcesSubmitted—⁦2026-02-23⁩ 13:34
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2026-02-24⁩ 11:14
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-25⁩ 12:21
4Portfolio manager reviewTechnical acceptanceDr. Noura M. Al-OtaibiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2026-03-01⁩ 13:28
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-03-04⁩ 13:10
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2026-03-08⁩ 09:42

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2026-02-24⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2026-02-25⁩

Portfolio manager review

Dr. Noura M. Al-Otaibi

Approved⁦2026-03-01⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2026-03-04⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2026-03-08⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Abdulmajeed R. Al-Dosari on ⁦2026-02-23⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2026-02-24⁩ at ⁦11:14⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-25⁩ at ⁦12:21⁩

  3. Technical acceptance

    Portfolio manager review

    Dr. Noura M. Al-Otaibi · Portfolio manager

    Approved · ⁦2026-03-01⁩ at ⁦13:28⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-03-04⁩ at ⁦13:10⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2026-03-08⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-03-16⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Abdulmajeed R. Al-Dosari

  2. V1Returned for edit⁦2026-02-23⁩

    First draft — returned to complete the cost and risks