Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-032On track5ClosureAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-03-31⁩
Hijri
2 Shawwal 1446 AH
ApprovedCRT-032-07Integrations

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-032
Project
HR Self-Service
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The deliverableAuto-filled

DeliverableAuto-filled
Integrations
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Abdulmajeed R. Al-Dosari
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦13%⁩
DueAuto-filled
⁦2025-04-06⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-032_3.3_v1.pdfV1Abdulmajeed R. Al-Dosari⁦2025-01-21⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Abdulmajeed R. Al-Dosari
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2024-012
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Abdulmajeed R. Al-DosariDirector General, Human ResourcesSubmitted—⁦2025-01-21⁩ 09:00
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-01-22⁩ 09:48
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Abdulmajeed R. Al-DosariApprovedInspected and accepted against the approved acceptance criteria.⁦2025-01-26⁩ 10:55
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-01-28⁩ 14:35
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-01-29⁩ 09:12

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-01-22⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2025-01-26⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-01-28⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-01-29⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Abdulmajeed R. Al-Dosari on ⁦2025-01-21⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-01-22⁩ at ⁦09:48⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Abdulmajeed R. Al-Dosari · Project owner

    Approved · ⁦2025-01-26⁩ at ⁦10:55⁩ · On behalf of Abdulmajeed R. Al-Dosari (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-01-28⁩ at ⁦14:35⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-01-29⁩ at ⁦09:12⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-01-21⁩

    PRJ-2026-032_3.3_v1.pdf

    Abdulmajeed R. Al-Dosari

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close