HR Self-Service
Add to watchlistEmployee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.
Budget (BAC)
Actual cost
94% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ClosureStage 5 of 5
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
- Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage
Project documents by stage
What each stage requires under the RFP, what has been filed and what is missing, and the evidence tied to deliverables.
Mandatory complete
3
of 9
- 3 of 9 mandatory documents due
- 6 mandatory documents missing
- 3 documents in the repository
A closed project — documents archived
Every project document moved to «Archive» when it closed, read-only under the retention policy.
Stages and required documents
For each of the five stages, what its gates and forms require: present, missing, or not yet due.
- 1Pre-start
Project proposal & feasibility studyMandatory· Missing
Approval gate G1
Priority & weight assessmentOptional· Missing
Annual work plan
- 2Initiation
Approved project charterMandatory· Present
HR Self-Service — project charterV1Initiation gate G2
Kick-off meeting minutesMandatory· Missing
Initiation gate G2
- 3Planning
Project management plan, schedule & baselineMandatory· Missing
Planning gate G3
Contract or purchase orderMandatory· Missing
Finance & procurement — when there is a contract
Technical studies & drawingsOptional· Missing
Project management plan
- 4Execution
Periodic update cards & status reportsMandatory· Missing
Periodic update card form
Deliverable completion certificatesMandatory· Missing
Deliverable completion certificate form
Corrective plan when off trackOptional· Missing
Corrective plan form
- 5Closure
Project closure & handover formMandatory· Present
Closure & handover form — HR Self-ServiceV1Closure gate G4
Lessons learnedMandatory· Present
Lessons learned — HR Self-ServiceV1Closure gate G4
Acceptance test resultsOptional· Missing
Deliverable acceptance
Evidence tied to deliverables
Each deliverable with its repository document and the files that prove it.
- 032-D1Project plan & baselinePRJ-2026-032_1.1_v1.pdfApprovedDeliverable
- 032-D2Monitoring & reportingPRJ-2026-032_1.2_v1.pdfApprovedDeliverable
- 032-D3Business requirementsPRJ-2026-032_2.1_v1.pdfApprovedDeliverable
- 032-D4Solution designPRJ-2026-032_2.2_v1.pdfApprovedDeliverable
- 032-D5Release 1PRJ-2026-032_3.1_v1.pdfApprovedDeliverable
- 032-D6Release 2PRJ-2026-032_3.2_v1.pdfApprovedDeliverable
- 032-D7IntegrationsPRJ-2026-032_3.3_v1.pdfApprovedDeliverable
- 032-D8System testingPRJ-2026-032_4.1_v1.pdfApprovedDeliverable
- 032-D9User acceptance testingPRJ-2026-032_4.2_v1.pdfApprovedDeliverable
- 032-D10Training & changePRJ-2026-032_5.1_v1.pdfApprovedDeliverable
- 032-D11Go-live & handoverPRJ-2026-032_5.2_v1.pdfApprovedDeliverable