HR Self-Service Subtask Last item under this branch 2025-09-21 100% HR Self-Service Planned: 2024-05-05 → 2025-09-30 Actual: 2024-05-05 → 2025-09-21
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2024-08-26 100% Management & governance Planned: 2024-05-05 → 2024-08-28 Actual: 2024-05-05 → 2024-08-26
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-07-14 100% Project plan & baseline Planned: 2024-05-05 → 2024-07-15 Actual: 2024-05-05 → 2024-07-14
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-08-26 100% Monitoring & reporting Planned: 2024-06-18 → 2024-08-28 Actual: 2024-06-17 → 2024-08-26
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-08-26 100% Project plan approved Planned: 2024-08-28 → 2024-08-28 Actual: 2024-08-26 → 2024-08-26 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2024-11-21 100% Analysis & design Planned: 2024-08-01 → 2024-11-24 Actual: 2024-07-31 → 2024-11-21
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-10-08 100% Business requirements Planned: 2024-08-01 → 2024-10-11 Actual: 2024-07-31 → 2024-10-08
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-11-21 100% Solution design Planned: 2024-09-15 → 2024-11-24 Actual: 2024-09-12 → 2024-11-21
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-11-21 100% Designs approved Planned: 2024-11-24 → 2024-11-24 Actual: 2024-11-21 → 2024-11-21 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-03-31 100% Build Planned: 2024-10-29 → 2025-04-06 Actual: 2024-10-26 → 2025-03-31
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-01-03 100% Release 1 Planned: 2024-10-29 → 2025-01-08 Actual: 2024-10-26 → 2025-01-03
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-02-16 100% Release 2 Planned: 2024-12-12 → 2025-02-21 Actual: 2024-12-08 → 2025-02-16
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-31 100% Integrations Planned: 2025-01-25 → 2025-04-06 Actual: 2025-01-21 → 2025-03-31
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-03-31 100% Build complete Planned: 2025-04-06 → 2025-04-06 Actual: 2025-03-31 → 2025-03-31 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-06-26 100% Testing & acceptance Planned: 2025-03-11 → 2025-07-04 Actual: 2025-03-05 → 2025-06-26
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-14 100% System testing Planned: 2025-03-11 → 2025-05-20 Actual: 2025-03-05 → 2025-05-14
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-26 100% User acceptance testing Planned: 2025-04-24 → 2025-07-04 Actual: 2025-04-18 → 2025-06-26
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-06-26 100% Testing & acceptance complete Planned: 2025-07-04 → 2025-07-04 Actual: 2025-06-26 → 2025-06-26 Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-21 100% Launch & handover Planned: 2025-06-07 → 2025-09-30 Actual: 2025-05-31 → 2025-09-21
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-09 100% Training & change Planned: 2025-06-07 → 2025-08-17 Actual: 2025-05-31 → 2025-08-09
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-21 100% Go-live & handover Planned: 2025-07-21 → 2025-09-30 Actual: 2025-07-13 → 2025-09-21
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-21 100% Final handover Planned: 2025-09-30 → 2025-09-30 Actual: 2025-09-21 → 2025-09-21 Final handover