PRJ-2026-032On track5ClosureAgile

HR Self-Service

Add to watchlist

Employee self-service for 34 HR procedures, from leave to secondments, linked to the Masar platform.

Budget (BAC)

SAR 11.4M

Actual cost

SAR 10.8M

⁦94%⁩ of budget

Progress

⁦100%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 10.8M

SPI · CPI

1.00Schedule performance index · 1.001.06Cost performance index · 1.06

Forecast finish

⁦2025-09-21⁩

On baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 March 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 May 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate26 July 2024Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate20 August 2025Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2024-05-12⁩
Hijri
4 Dhuʻl-Qiʻdah 1445 AH
ApprovedMTG-KO-032Kick-off — HR Self-Service

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-032
Project
HR Self-Service
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — HR Self-Service
Date and timeAuto-filled
⁦2024-05-12⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Dana S. Al-Saleh

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Sarah A. Al-QarniHead, Corporate Support Sector
Abdulmajeed R. Al-DosariDirector General, Human Resources
Dana S. Al-SalehDirector, Enterprise Systems & Integration
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Sarah A. Al-QarniProject sponsorSponsors the project, decides escalations and material changes
Abdulmajeed R. Al-DosariProject ownerApproves the requirements and accepts the deliverables
Dana S. Al-SalehProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedDana S. Al-Saleh⁦2024-08-28⁩Done
Designs approvedDana S. Al-Saleh⁦2024-11-24⁩Done
Build completeDana S. Al-Saleh⁦2025-04-06⁩Done
Testing & acceptance completeDana S. Al-Saleh⁦2025-07-04⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2024-07-26⁩
Start confirmed
Sarah A. Al-Qarni · ⁦2024-05-13⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2024-05-13⁩ 10:19
2Chair’s approval (sponsor)Technical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2024-05-14⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-05-15⁩ 14:53

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2024-05-15⁩

Chair’s approval (sponsor)

Sarah A. Al-Qarni

Approved⁦2024-05-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2024-05-13⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-05-15⁩ at ⁦14:53⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2024-05-14⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-05-12⁩