PRJ-2026-034At risk4ExecutionConstruction
Arar Vocational Qualification Centre
Add to watchlistA training and skills-test centre for the Northern Borders on land allocated by the municipality, with utilities and access roads.
Project managerEng. Ibrahim A. Al-GhamdiProject sponsorEng. Turki A. Al-AnaziProgrammeHeadquarters & Major Qualification Centres Programme
Early warning: 55% chance of slipping within 60 days
Budget (BAC)
SAR 238M
Actual cost
SAR 81.8M
34% of budget
Progress
33%Awaiting acceptance 12%
Estimate at completion
SAR 247.9M
SAR +9.9M
SPI · CPI
0.89Schedule performance index · 0.890.96Cost performance index · 0.96
Forecast finish
2027-09-28
28 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure29 June 2027
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate7 May 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate6 July 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 November 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate29 June 2027Closure · Not startedClosure · Not started
Work breakdown structure
The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.
Structure levels
Pick a level to open the tree to that depth
Allotted to work230.9M17 elements
Unallocated contingency7.1MSAR 11.9M
Budget at completion238MPRJ-2026-034
Weighted progress33%Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Total33%230.8681.81