Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-036On track5ClosureConstruction

Khamis Mushait Training Centre Rehabilitation

Add to watchlist

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-01-18⁩
Hijri
18 Rajab 1446 AH
ApprovedCRT-036-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Khamis Mushait Training Centre Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Waleed O. Al-Juhani

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Waleed O. Al-Juhani
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦3%⁩
DueAuto-filled
⁦2025-01-10⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-036_1.1_v1.pdfV1Eng. Waleed O. Al-Juhani⁦2024-10-06⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Bandar M. Al-Shammari
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2024-022
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2024-10-06⁩ 13:46
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-10-07⁩ 09:42
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Eng. Bandar M. Al-ShammariApprovedInspected and accepted against the approved acceptance criteria.⁦2024-10-09⁩ 10:49
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2024-10-13⁩ 10:49
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-10-14⁩ 11:26

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2024-10-07⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2024-10-09⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2024-10-13⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2024-10-14⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2024-10-06⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-10-07⁩ at ⁦09:42⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Bandar M. Al-Shammari · Project owner

    Approved · ⁦2024-10-09⁩ at ⁦10:49⁩ · On behalf of Eng. Bandar M. Al-Shammari (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2024-10-13⁩ at ⁦10:49⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-10-14⁩ at ⁦11:26⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2024-10-06⁩

    PRJ-2026-036_1.1_v1.pdf

    Eng. Waleed O. Al-Juhani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close