PRJ-2026-036On track5ClosureConstruction

Khamis Mushait Training Centre Rehabilitation

Add to watchlist

Rehabilitating the Khamis Mushait training centre — fire and alarm systems and training halls.

Budget (BAC)

SAR 67M

Actual cost

SAR 64.3M

⁦96%⁩ of budget

Progress

⁦97%⁩Awaiting acceptance ⁦3%⁩

Estimate at completion

SAR 66.3M

SPI · CPI

0.98Schedule performance index · 0.981.01Cost performance index · 1.01

Forecast finish

⁦2026-11-12⁩

12 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate7 August 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate6 October 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate4 February 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate1 September 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
SCA-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
Hijri
17 Jumada I 1448 AH
DraftPRJ-2026-036Khamis Mushait Training Centre Rehabilitation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-036
Project
Khamis Mushait Training Centre Rehabilitation
Portfolio
Building Rehabilitation & Sustainability Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Waleed O. Al-Juhani

1PerformanceAuto-filled

Approved budget

SAR 67M

Actual cost

SAR 64.3M

Cost variance

SAR +2.7M

Schedule variance

+12 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenEng. Bandar M. Al-ShammariFinal acceptance of every deliverable
Financial settlementOpenKhalid N. Al-MutairiSpend reconciled, commitments closed
Contracts closedOpenKhalid N. Al-MutairiContracts closed, retention released
Documents archivedOpenEng. Waleed O. Al-JuhaniDocuments archived with classification
Lessons learnedOpenEng. Waleed O. Al-JuhaniLessons-learned session
Benefits handed to their ownerOpenEng. Bandar M. Al-ShammariBenefits handed to their owner with a measurement plan
Final reportOpenEng. Waleed O. Al-JuhaniFinal report and its approval
BenefitNew ownerHandover
Training capacity after rehabilitationEng. Waleed O. Al-JuhaniPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableEng. Bandar M. Al-Shammari⁦2026-11-02⁩
Financial settlement — Spend reconciled, commitments closedKhalid N. Al-Mutairi⁦2026-12-02⁩
Contracts closed — Contracts closed, retention releasedKhalid N. Al-Mutairi⁦2026-12-12⁩
Documents archived — Documents archived with classificationEng. Waleed O. Al-Juhani⁦2026-12-07⁩
Lessons learned — Lessons-learned sessionEng. Waleed O. Al-Juhani⁦2026-11-27⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planEng. Bandar M. Al-Shammari⁦2026-11-22⁩
Final report — Final report and its approvalEng. Waleed O. Al-Juhani⁦2026-12-17⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Later

Handover accepted — project owner

Eng. Bandar M. Al-Shammari

Later

Final financial settlement

Munirah A. Al-Khalidi

Later

Contracts closed, guarantees released

Mazen A. Al-Hazmi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

  2. Technical acceptance

    Handover accepted — project owner

    Eng. Bandar M. Al-Shammari · Project owner
  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

  4. Financial approval

    Contracts closed, guarantees released

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee
Waiting on Eng. Waleed O. Al-Juhani

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Eng. Waleed O. Al-Juhani

Only one version so far.