SCA/2025/003
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SAR 6.8M — if approved the value becomes SAR 48M
64% of the current value paid
Paid
26.4Mof a current value of SAR 41.2M
Value of each certificate
The last 13 — gross and net
Approved: 13
Count: 13 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 13September 2026 | 2026-10-06 | 980K | 98K | 98K | 117.6K | 901.6K | Approved | |
| Certificate 12July 2026 | 2026-08-20 | 1.5M | 147K | 147K | 176.4K | 1.4M | Approved | |
| Certificate 11June 2026 | 2026-07-04 | 1.7M | 174K | 174K | 208.8K | 1.6M | Approved | |
| Certificate 10April 2026 | 2026-05-18 | 2.5M | 248K | 248K | 297.6K | 2.3M | Approved | |
| Certificate 9March 2026 | 2026-03-31 | 2.4M | 242K | 242K | 290.4K | 2.2M | Approved | |
| Certificate 8January 2026 | 2026-02-12 | 2.6M | 260K | 260K | 312K | 2.4M | Approved | |
| Certificate 7December 2025 | 2025-12-27 | 3.1M | 306K | 306K | 367.2K | 2.8M | Approved | |
| Certificate 6October 2025 | 2025-11-10 | 2.5M | 245K | 245K | 294K | 2.3M | Approved | |
| Certificate 5September 2025 | 2025-09-24 | 2.6M | 260K | 260K | 312K | 2.4M | Approved | |
| Certificate 4July 2025 | 2025-08-08 | 2.4M | 239K | 239K | 286.8K | 2.2M | Approved | |
| Certificate 3June 2025 | 2025-06-21 | 1.7M | 171K | 171K | 205.2K | 1.6M | Approved | |
| Certificate 2April 2025 | 2025-05-05 | 1.5M | 153K | 153K | 183.6K | 1.4M | Approved | |
| Certificate 1February 2025 | 2025-03-19 | 970K | 97K | 97K | 116.4K | 892.4K | Approved |