Project status card
28 October 2026 · 17 Jumada I 1448 AH
Mimar — Unified Building Journey & Government Integration
PRJ-2026-011 · Digital Transformation Sector · External · WP-2026-011
- Progress
- 6% / 6%
- SPI · CPI
- 1.00 · 1.00
- Spend
- SAR 1.4M / SAR 24M
- Estimate at completion
- SAR 24M
Schedule
Planned to date 6%
Forecast finish: 2027-12-302 Shaʻban 1449 AH · On time
SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00Health dimensions
Last update: 2026-10-209 Jumada I 1448 AH · Up to date
Deliverables
1 of 1 due deliverables accepted on time (100%)
Next milestones
- Project plan approved2026-12-0424 Jumada II 1448 AH
- Designs approved2027-03-0223 Ramadan 1448 AH
- Build complete2027-07-128 Safar 1449 AH
- Testing & acceptance complete2027-10-088 Jumada I 1449 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 24M: 1 on track and 0 red or critical. Weighted progress is 6% against 6% planned, spend SAR 1.4M, and EAC SAR 24M (SAR 0M under).
No project is more than a month behind baseline.