PRJ-2026-011On track3PlanningWaterfall

Mimar — Unified Building Journey & Government Integration

Add to watchlist

One journey for contractors and owners from permit to handover, linked with Balady, Etimad, Qiwa and the commercial register.

Budget (BAC)

SAR 24M

Actual cost

SAR 1.4M

⁦6%⁩ of budget

Progress

⁦6%⁩Awaiting acceptance ⁦4%⁩

Estimate at completion

SAR 24M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-30⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution30 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 May 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 July 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate30 September 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
SCA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2026-01-31⁩
Hijri
12 Shaʻban 1447 AH
ApprovedPRJ-2026-011Mimar — Unified Building Journey & Government Integration

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-011
Project
Mimar — Unified Building Journey & Government Integration
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The resultAuto-filled

Priority score

66 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the SCA strategy⁦20%⁩4.316.5
Value added to the contracting sector⁦12%⁩3.88.4
Financial return & sustainability⁦8%⁩3.44.8
Urgency⁦10%⁩3.25.5
Regulatory requirement⁦10%⁩3.66.5
Risk⁦7%⁩1.95.4
Complexity⁦6%⁩1.94.7
Resource requirement⁦5%⁩1.05.0
Impact on contractors & beneficiaries⁦14%⁩2.96.7
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.11.4
Total⁦100%⁩—66

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2026-01-31⁩ 11:26
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-02-01⁩ 09:30
3Portfolio manager reviewTechnical acceptanceEng. Nayef H. Al-BuqamiPortfolio managerApproved—⁦2026-02-03⁩ 10:37
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2026-02-08⁩ 11:44

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2026-02-01⁩

Portfolio manager review

Eng. Nayef H. Al-Buqami

Approved⁦2026-02-03⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2026-02-08⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-01-31⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-02-01⁩ at ⁦09:30⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Nayef H. Al-Buqami · Portfolio manager

    Approved · ⁦2026-02-03⁩ at ⁦10:37⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2026-02-08⁩ at ⁦11:44⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2026-01-31⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.