Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-013At risk4ExecutionConstruction

Smart Test-hall Proctoring & Access Control

Add to watchlist

4,200 cameras and smart entry gates across HQ, branches and qualification centres, with a central monitoring room and automatic identity checks for test takers, starting at the Qassim centre.

Early warning: ⁦58%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 74M

Actual cost

SAR 62.2M

⁦84%⁩ of budget

Progress

⁦79%⁩Awaiting acceptance ⁦9%⁩

Estimate at completion

SAR 78.7M

SAR +4.7M

SPI · CPI

0.88Schedule performance index · 0.880.94Cost performance index · 0.94

Forecast finish

⁦2026-12-15⁩

45 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure11 September 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate18 December 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 February 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate27 May 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate11 September 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-02-23⁩
Hijri
24 Shaʻban 1446 AH
ApprovedMTG-KO-013Kick-off — Smart Test-hall Proctoring & Access Control

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-013
Project
Smart Test-hall Proctoring & Access Control
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Corporate Support Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Waleed O. Al-Juhani

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Smart Test-hall Proctoring & Access Control
Date and timeAuto-filled
⁦2025-02-23⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Eng. Waleed O. Al-Juhani

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Turki A. Al-AnaziHead, Qualification & Training Sector
Eng. Bandar M. Al-ShammariDirector General, Facilities & Premises
Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & Maintenance
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Eng. Bandar M. Al-ShammariDirector General, Facilities & Premises

2Roles

PersonRoleDuty
Eng. Turki A. Al-AnaziProject sponsorSponsors the project, decides escalations and material changes
Eng. Bandar M. Al-ShammariProject ownerApproves the requirements and accepts the deliverables
Eng. Waleed O. Al-JuhaniProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Eng. Bandar M. Al-ShammariProject sponsorDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedEng. Waleed O. Al-Juhani⁦2025-06-24⁩Done
Designs approvedEng. Waleed O. Al-Juhani⁦2025-10-01⁩Done
Build completeEng. Waleed O. Al-Juhani⁦2026-02-26⁩Done
Testing & acceptance completeEng. Waleed O. Al-Juhani⁦2026-07-24⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-05-27⁩
Start confirmed
Eng. Turki A. Al-Anazi · ⁦2025-02-24⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Waleed O. Al-JuhaniDirector, Facilities Operations & MaintenanceSubmitted—⁦2025-02-24⁩ 09:12
2Chair’s approval (sponsor)Technical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2025-02-25⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-02-25⁩ 13:16

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-02-25⁩

Chair’s approval (sponsor)

Eng. Turki A. Al-Anazi

Approved⁦2025-02-25⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Eng. Waleed O. Al-Juhani on ⁦2025-02-24⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-02-25⁩ at ⁦13:16⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2025-02-25⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-02-23⁩

    The minutes as taken

    Eng. Waleed O. Al-Juhani

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close