Smart Test-hall Proctoring & Access Control Subtask Last item under this branch 2027-01-11 79% Smart Test-hall Proctoring & Access Control Planned: 2025-02-16 → 2026-10-31 Forecast: 2025-02-16 → 2027-01-11 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-08-03 100% Management & governance Planned: 2025-02-16 → 2025-06-24 Actual: 2025-02-16 → 2025-08-03
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-30 100% Project plan & baseline Planned: 2025-02-16 → 2025-05-06 Actual: 2025-02-16 → 2025-05-30
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-03 100% Monitoring & reporting Planned: 2025-04-06 → 2025-06-24 Actual: 2025-04-21 → 2025-08-03
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-08-03 100% Project plan approved Planned: 2025-06-24 → 2025-06-24 Actual: 2025-08-03 → 2025-08-03 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-12-10 100% Design & permits Planned: 2025-05-26 → 2025-10-01 Actual: 2025-06-25 → 2025-12-10
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-10-06 100% Detailed design Planned: 2025-05-26 → 2025-08-13 Actual: 2025-06-25 → 2025-10-06
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-10 100% Permits & approvals Planned: 2025-07-14 → 2025-10-01 Actual: 2025-08-28 → 2025-12-10
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-10 100% Designs approved Planned: 2025-10-01 → 2025-10-01 Actual: 2025-12-10 → 2025-12-10 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-06-21 100% Civil works Planned: 2025-09-01 → 2026-02-26 Actual: 2025-11-01 → 2026-06-21
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-12 100% Site works & excavation Planned: 2025-09-01 → 2025-11-19 Actual: 2025-11-01 → 2026-02-12
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-17 100% Structure Planned: 2025-10-21 → 2026-01-08 Actual: 2026-01-04 → 2026-04-17
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-21 100% Finishes Planned: 2025-12-09 → 2026-02-26 Actual: 2026-03-10 → 2026-06-21
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-21 100% Build complete Planned: 2026-02-26 → 2026-02-26 Actual: 2026-06-21 → 2026-06-21 Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-22 77% MEP works Planned: 2026-01-28 → 2026-07-24 Forecast: 2026-05-06 → 2026-12-22 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-24 100% Supply Planned: 2026-01-28 → 2026-04-17 Actual: 2026-05-13 → 2026-08-24
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Installation Planned: 2026-03-18 → 2026-06-05 Actual: 2026-07-17 → 2026-10-26
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-22 30% Testing & commissioning Planned: 2026-05-06 → 2026-07-24 Forecast: 2026-05-06 → 2026-12-22 Float: 0d Drag to change its duration +151
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-22 0% Testing & acceptance complete Planned: 2026-07-24 → 2026-07-24 Forecast: 2026-12-22 → 2026-12-22 Float: 20d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-11 0% Handover Planned: 2026-06-25 → 2026-10-31 Forecast: 2026-12-16 → 2027-01-11 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-01 0% Provisional acceptance Planned: 2026-06-25 → 2026-09-12 Forecast: 2026-12-16 → 2027-01-01 Float: 0d Drag to change its dates +111
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-11 0% Final acceptance Planned: 2026-08-13 → 2026-10-31 Forecast: 2026-12-26 → 2027-01-11 Float: 0d Drag to change its dates +72
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-11 0% Final handover Planned: 2026-10-31 → 2026-10-31 Forecast: 2027-01-11 → 2027-01-11 Float: 0d Drag to change its dates Final handover