Muqawil Mobile App — Release 3

Add to watchlist

A mobile app for contractors’ most-used services, with instant renewal alerts and a digital wallet for the membership card and certificates.

Budget (BAC)

SAR 12.6M

Actual cost

SAR 7.8M

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 12.1M

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Muqawil Mobile App — Release 3

PRJ-2026-015 · Services & Membership Sector · Strategic · WP-2025-015

On track4ExecutionProject manager: Karim Haddad · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦64%⁩ / ⁦63%⁩
SPI · CPI
1.02 · 1.04
Spend
SAR 7.8M / SAR 12.6M
Estimate at completion
SAR 12.1M

Schedule

⁦1%⁩ ahead⁦64%⁩

Planned to date ⁦63%⁩

Forecast finish: 2027-01-2820 Shaʻban 1448 AH · On time

SPI1.02Schedule performance index · 1.02CPI1.04Cost performance index · 1.04

Health dimensions

On track

Last update: 2026-10-2615 Jumada I 1448 AH · Up to date

Deliverables

⁦6⁩ of ⁦8⁩ due deliverables accepted on time (⁦75%⁩)

Next milestones

  • Build complete2026-11-111 Jumada II 1448 AH
  • Testing & acceptance complete2026-12-1910 Rajab 1448 AH
  • Final handover2027-01-3123 Shaʻban 1448 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 12.6M: 1 on track and 0 red or critical. Weighted progress is 64% against 63% planned, spend SAR 7.8M, and EAC SAR 12.1M (SAR 0.5M under).

No project is more than a month behind baseline.

Saudi Contractors Authority · prepared by Karim Haddad in MunjazInternal

Status: On track ·Project page