Project status card
28 October 2026 · 17 Jumada I 1448 AH
Muqawil Mobile App — Release 3
PRJ-2026-015 · Services & Membership Sector · Strategic · WP-2025-015
- Progress
- 64% / 63%
- SPI · CPI
- 1.02 · 1.04
- Spend
- SAR 7.8M / SAR 12.6M
- Estimate at completion
- SAR 12.1M
Schedule
Planned to date 63%
Forecast finish: 2027-01-2820 Shaʻban 1448 AH · On time
SPI1.02Schedule performance index · 1.02CPI1.04Cost performance index · 1.04Health dimensions
Last update: 2026-10-2615 Jumada I 1448 AH · Up to date
Deliverables
6 of 8 due deliverables accepted on time (75%)
Next milestones
- Build complete2026-11-111 Jumada II 1448 AH
- Testing & acceptance complete2026-12-1910 Rajab 1448 AH
- Final handover2027-01-3123 Shaʻban 1448 AH
Top risks
- None
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 12.6M: 1 on track and 0 red or critical. Weighted progress is 64% against 63% planned, spend SAR 7.8M, and EAC SAR 12.1M (SAR 0.5M under).
No project is more than a month behind baseline.