PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Secure Enterprise Network

PRJ-2026-018 · Digital Transformation Sector · Operational · WP-2025-018

At risk4ExecutionProject manager: Eng. Omar H. Bawazir · Sponsor: Eng. Majed S. Al-Rasheed
Progress
⁦55%⁩ / ⁦63%⁩
SPI · CPI
0.87 · 0.97
Spend
SAR 74.8M / SAR 132M
Estimate at completion
SAR 136.1M

Schedule

⁦8%⁩ behind⁦55%⁩

Planned to date ⁦63%⁩

Forecast finish: 2027-03-0526 Ramadan 1448 AH · 33 days late

SPI0.87Schedule performance index · 0.87CPI0.97Cost performance index · 0.97

Health dimensions

At risk

Last update: 2026-09-2110 Rabiʻ II 1448 AH · Update overdue

Deliverables

⁦6⁩ of ⁦10⁩ due deliverables accepted on time (⁦60%⁩)

Next milestones

  • Build complete2026-11-111 Jumada II 1448 AH
  • Testing & acceptance complete2027-01-168 Shaʻban 1448 AH
  • Final handover2027-03-0122 Ramadan 1448 AH

Top risks

  • Municipal objections to trenching in built-up districts12
  • Higher reinstatement costs after network trenching9

Open impediments

  • Trenching permit suspended in Al-Rawdah district · Open

Decisions and changes waiting

  • CR-2026-014 · Re-route the network in Al-Rawdah district

Copilot summary

The scope holds 1 project with a budget of SAR 132M: 0 on track and 0 red or critical. Weighted progress is 55% against 63% planned, spend SAR 74.8M, and EAC SAR 136.1M (SAR 4.1M over).

1 project is more than a month behind baseline; the worst: Secure Enterprise Network (33 days).

Saudi Contractors Authority · prepared by Eng. Omar H. Bawazir in MunjazInternal

Status: At risk ·Project page