Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-02-27⁩
Hijri
10 Ramadan 1447 AH
ApprovedCRT-018-03Detailed design

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Secure Enterprise Network
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The deliverableAuto-filled

DeliverableAuto-filled
Detailed design
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Nayef H. Al-Buqami
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦8%⁩
DueAuto-filled
⁦2025-11-07⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-018_2.1_v1.pdfV1Eng. Nayef H. Al-Buqami⁦2025-10-20⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Nayef H. Al-Buqami
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-020
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Nayef H. Al-BuqamiDirector General, Information TechnologySubmitted—⁦2025-10-20⁩ 09:00
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-10-21⁩ 11:20
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Nayef H. Al-BuqamiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-10-22⁩ 12:27
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-10-26⁩ 12:51
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-27⁩ 13:28

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-10-21⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2025-10-22⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-10-26⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-10-27⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Nayef H. Al-Buqami on ⁦2025-10-20⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-10-21⁩ at ⁦11:20⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2025-10-22⁩ at ⁦12:27⁩ · On behalf of Eng. Nayef H. Al-Buqami (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-10-26⁩ at ⁦12:51⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-27⁩ at ⁦13:28⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-10-20⁩

    PRJ-2026-018_2.1_v1.pdf

    Eng. Nayef H. Al-Buqami

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close