Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstruction

Secure Enterprise Network

Add to watchlist

Fibre and backup links connecting HQ, the two branches and the qualification centres — 14 sites — to the Authority’s secure network.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 132M

Actual cost

SAR 74.8M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 136.1M

SAR +4.1M

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
SCA-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-08-08⁩
Hijri
25 Safar 1448 AH
ApprovedCRT-018-05Site works & excavation

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-018
Project
Secure Enterprise Network
Portfolio
Headquarters & Regional Centres Portfolio
Sector
Digital Transformation Sector
Sponsor
Eng. Majed S. Al-Rasheed
Project manager
Eng. Omar H. Bawazir

1The deliverableAuto-filled

DeliverableAuto-filled
Site works & excavation
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Majed S. Al-Rasheed
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦16%⁩
DueAuto-filled
⁦2026-02-15⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-018_3.1_v1.pdfV1Eng. Majed S. Al-Rasheed⁦2026-03-31⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Nayef H. Al-Buqami
Accepted byAuto-filled
Eng. Majed S. Al-Rasheed
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2025-020
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Majed S. Al-RasheedHead, Digital Transformation SectorSubmitted—⁦2026-03-31⁩ 11:14
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-04-01⁩ 13:34
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Majed S. Al-RasheedProject ownerOn behalf of Eng. Nayef H. Al-BuqamiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-04-06⁩ 14:41
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-04-08⁩ 14:05
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-04-09⁩ 09:42

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-04-01⁩

Inspection & technical acceptance — owner

Eng. Majed S. Al-Rasheed

Approved⁦2026-04-06⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-04-08⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-04-09⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Majed S. Al-Rasheed on ⁦2026-03-31⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-04-01⁩ at ⁦13:34⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Nayef H. Al-Buqami · Project owner

    Approved · ⁦2026-04-06⁩ at ⁦14:41⁩ · On behalf of Eng. Nayef H. Al-Buqami (Eng. Majed S. Al-Rasheed)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-04-08⁩ at ⁦14:05⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-04-09⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-03-31⁩

    PRJ-2026-018_3.1_v1.pdf

    Eng. Majed S. Al-Rasheed

Only one version so far.