PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Irtiqaa Portal — Release 2

PRJ-2026-027 · Qualification & Training Sector · Strategic · WP-2025-027

At risk4ExecutionProject manager: Ghada A. Al-Shahrani · Sponsor: Sarah A. Al-Qarni
Progress
⁦63%⁩ / ⁦72%⁩
SPI · CPI
0.88 · 0.98
Spend
SAR 4.1M / SAR 6.4M
Estimate at completion
SAR 6.5M

Schedule

⁦9%⁩ behind⁦63%⁩

Planned to date ⁦72%⁩

Forecast finish: 2027-01-3123 Shaʻban 1448 AH · 31 days late

SPI0.88Schedule performance index · 0.88CPI0.98Cost performance index · 0.98

Health dimensions

At risk

Last update: 2026-09-2413 Rabiʻ II 1448 AH · Update overdue

Deliverables

⁦5⁩ of ⁦9⁩ due deliverables accepted on time (⁦56%⁩)

Next milestones

  • Build complete2026-11-111 Jumada II 1448 AH
  • Testing & acceptance complete2026-12-2112 Rajab 1448 AH
  • Final handover2027-01-3022 Shaʻban 1448 AH

Top risks

  • Low uptake of the Irtiqaa self-assessment among small contractors9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 6.4M: 0 on track and 0 red or critical. Weighted progress is 63% against 72% planned, spend SAR 4.1M, and EAC SAR 6.5M (SAR 0.1M over).

1 project is more than a month behind baseline; the worst: Irtiqaa Portal — Release 2 (31 days).

Saudi Contractors Authority · prepared by Ghada A. Al-Shahrani in MunjazInternal

Status: At risk ·Project page