Project status card
28 October 2026 · 17 Jumada I 1448 AH
Irtiqaa Portal — Release 2
PRJ-2026-027 · Qualification & Training Sector · Strategic · WP-2025-027
- Progress
- 63% / 72%
- SPI · CPI
- 0.88 · 0.98
- Spend
- SAR 4.1M / SAR 6.4M
- Estimate at completion
- SAR 6.5M
Schedule
Planned to date 72%
Forecast finish: 2027-01-3123 Shaʻban 1448 AH · 31 days late
SPI0.88Schedule performance index · 0.88CPI0.98Cost performance index · 0.98Health dimensions
Last update: 2026-09-2413 Rabiʻ II 1448 AH · Update overdue
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2026-11-111 Jumada II 1448 AH
- Testing & acceptance complete2026-12-2112 Rajab 1448 AH
- Final handover2027-01-3022 Shaʻban 1448 AH
Top risks
- Low uptake of the Irtiqaa self-assessment among small contractors9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 6.4M: 0 on track and 0 red or critical. Weighted progress is 63% against 72% planned, spend SAR 4.1M, and EAC SAR 6.5M (SAR 0.1M over).
1 project is more than a month behind baseline; the worst: Irtiqaa Portal — Release 2 (31 days).