PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
SCA-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-10-31⁩
Hijri
9 Jumada I 1447 AH
ApprovedPRJ-2026-027Irtiqaa Portal — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-027
Project
Irtiqaa Portal — Release 2
Portfolio
Institutional Excellence & Governance Portfolio
Sector
Qualification & Training Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Ghada A. Al-Shahrani

1Objective

Background

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Project objectives

  1. Leadership and human capital

2Scope

In scope

  • A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-11-19⁩
Main deliverable — stage 1⁦2026-06-07⁩
Main deliverable — final stage⁦2026-11-02⁩
Final report⁦2026-12-31⁩
MilestoneDate
Charter approved⁦2025-10-31⁩
Contract signed⁦2026-01-09⁩
50% of works complete⁦2026-06-07⁩
Provisional acceptance⁦2026-11-27⁩
Closure⁦2026-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Sarah A. Al-Qarni
Project ownerAuto-filled
Abdulmajeed R. Al-Dosari
Project managerAuto-filled
Ghada A. Al-Shahrani
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change Control BoardApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 4.6M
Supervision & consultingSAR 900K
Internal teamSAR 600K
Contingency reserve (5%)SAR 300K
Approved budgetSAR 6.4M

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2025-10-22⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-10-25⁩ 12:30
3Project ownerTechnical acceptanceAbdulmajeed R. Al-DosariProject ownerApproved—⁦2025-10-28⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-10-29⁩ 11:10
5Sponsor approvalTechnical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-10-31⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-10-25⁩

Project owner

Abdulmajeed R. Al-Dosari

Approved⁦2025-10-28⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-10-29⁩

Sponsor approval

Sarah A. Al-Qarni

Approved⁦2025-10-31⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-10-22⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-10-25⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Abdulmajeed R. Al-Dosari · Project owner

    Approved · ⁦2025-10-28⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-10-29⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-10-31⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-10-31⁩

    Approved version

    • PMO comments addressed

    Ghada A. Al-Shahrani

  2. V1Returned for edit⁦2025-10-12⁩

    First draft

    • Returned to detail the budget

    Ghada A. Al-Shahrani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close