Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-027At risk4ExecutionHybrid

Irtiqaa Portal — Release 2

Add to watchlist

A portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.

Budget (BAC)

SAR 6.4M

Actual cost

SAR 4.1M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.5M

SAR +131K

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
1At risk
2Late
Average delay64 days
Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-08-07⁩Forecast / actual: ⁦2026-11-11⁩Delay: 96 daysG3 +96
Executive
Project plan approvedPlanned: ⁦2026-02-05⁩Forecast / actual: ⁦2026-03-24⁩Delay: 47 daysG1 +47
Payment
Final handoverPlanned: ⁦2026-12-31⁩Forecast / actual: ⁦2027-01-30⁩Delay: 30 daysG5 +30
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-19⁩Forecast / actual: ⁦2026-12-21⁩Delay: 63 daysG4 +63
Project
Designs approvedPlanned: ⁦2026-04-19⁩Forecast / actual: ⁦2026-07-11⁩Delay: 83 daysG2 +83

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2026-02-05⁩⁦2026-03-24⁩⁦+47⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAchieved1Approved
Designs approvedMS-G2Project⁦2026-04-19⁩⁦2026-07-11⁩⁦+83⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-08-07⁩⁦2026-11-11⁩⁦+96⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-10-19⁩⁦2026-12-21⁩⁦+63⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saLate0Not requested
Final handoverMS-G5Payment⁦2026-12-31⁩⁦2027-01-30⁩⁦+30⁩ daysGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦63%⁩

Awaiting acceptance

⁦10%⁩

Not handed in

⁦27%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline027-D1⁦5%⁩CRT-027-01ApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAbdulmajeed R. Al-Dosari⁦2025-12-30⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting027-D2⁦5%⁩CRT-027-02ApprovedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.saAbdulmajeed R. Al-Dosari⁦2026-02-05⁩V1⁦3⁩ of ⁦3⁩
Business requirements027-D3⁦11%⁩CRT-027-03ApprovedAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.saAbdulmajeed R. Al-Dosari⁦2026-03-14⁩V1⁦3⁩ of ⁦3⁩
Solution design027-D4⁦10%⁩CRT-027-04ApprovedSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saAbdulmajeed R. Al-Dosari⁦2026-04-19⁩V1⁦3⁩ of ⁦3⁩
Release 1027-D5⁦16%⁩CRT-027-05ApprovedSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saAbdulmajeed R. Al-Dosari⁦2026-05-26⁩V1⁦3⁩ of ⁦3⁩
Release 2027-D6⁦16%⁩CRT-027-06ApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAbdulmajeed R. Al-Dosari⁦2026-07-01⁩V1⁦3⁩ of ⁦3⁩
Integrations027-D7⁦10%⁩—Under reviewAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.saAbdulmajeed R. Al-Dosari⁦2026-08-07⁩V1⁦1⁩ of ⁦3⁩
System testing027-D8⁦8%⁩—DraftGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.saAbdulmajeed R. Al-Dosari⁦2026-09-12⁩V0⁦0⁩ of ⁦3⁩
User acceptance testing027-D9⁦7%⁩—DraftAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.saAbdulmajeed R. Al-Dosari⁦2026-10-19⁩V0⁦0⁩ of ⁦3⁩
Training & change027-D10⁦6%⁩—DraftAbdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.saAbdulmajeed R. Al-Dosari⁦2026-11-24⁩V0⁦0⁩ of ⁦3⁩
Go-live & handover027-D11⁦6%⁩—DraftSarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.saAbdulmajeed R. Al-Dosari⁦2026-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close