Irtiqaa Portal — Release 2
Add to watchlistA portal to grow contractors’ capability: a self-assessment, a development plan and qualification programmes matched to the gaps.
Budget (BAC)
Actual cost
64% of budget
Progress
Estimate at completion
SAR +131K
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-02-05 | 2026-03-24 | +47 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-07-11 | +83 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-08-07 | 2026-11-11 | +96 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-19 | 2026-12-21 | +63 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-30 | +30 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
63%Awaiting acceptance
10%Not handed in
27%Deliverable flow
Display options
| Project plan & baseline027-D1 | 5% | CRT-027-01 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Abdulmajeed R. Al-Dosari | 2025-12-30 | V1 | 3 of 3 |
| Monitoring & reporting027-D2 | 5% | CRT-027-02 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | Abdulmajeed R. Al-Dosari | 2026-02-05 | V1 | 3 of 3 |
| Business requirements027-D3 | 11% | CRT-027-03 | Approved | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | Abdulmajeed R. Al-Dosari | 2026-03-14 | V1 | 3 of 3 |
| Solution design027-D4 | 10% | CRT-027-04 | Approved | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Abdulmajeed R. Al-Dosari | 2026-04-19 | V1 | 3 of 3 |
| Release 1027-D5 | 16% | CRT-027-05 | Approved | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Abdulmajeed R. Al-Dosari | 2026-05-26 | V1 | 3 of 3 |
| Release 2027-D6 | 16% | CRT-027-06 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Abdulmajeed R. Al-Dosari | 2026-07-01 | V1 | 3 of 3 |
| Integrations027-D7 | 10% | — | Under review | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | Abdulmajeed R. Al-Dosari | 2026-08-07 | V1 | 1 of 3 |
| System testing027-D8 | 8% | — | Draft | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Qualification Programmes & CapabilityP-029g.alshahrani@sca.sa | Abdulmajeed R. Al-Dosari | 2026-09-12 | V0 | 0 of 3 |
| User acceptance testing027-D9 | 7% | — | Draft | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | Abdulmajeed R. Al-Dosari | 2026-10-19 | V0 | 0 of 3 |
| Training & change027-D10 | 6% | — | Draft | Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesP-019am.aldosari@sca.sa | Abdulmajeed R. Al-Dosari | 2026-11-24 | V0 | 0 of 3 |
| Go-live & handover027-D11 | 6% | — | Draft | Sarah A. Al-QarniSarah A. Al-QarniHead, Corporate Support SectorP-012s.alqarni@sca.sa | Abdulmajeed R. Al-Dosari | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |