Irtiqaa Portal — Release 2 Subtask Last item under this branch 2027-01-30 63% Irtiqaa Portal — Release 2 Planned: 2025-11-02 → 2026-12-31 Forecast: 2025-11-02 → 2027-01-30 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-03-24 100% Management & governance Planned: 2025-11-02 → 2026-02-05 Actual: 2025-11-02 → 2026-03-24
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-28 100% Project plan & baseline Planned: 2025-11-02 → 2025-12-30 Actual: 2025-11-02 → 2026-01-28
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-24 100% Monitoring & reporting Planned: 2025-12-09 → 2026-02-05 Actual: 2025-12-27 → 2026-03-24
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-03-24 100% Project plan approved Planned: 2026-02-05 → 2026-02-05 Actual: 2026-03-24 → 2026-03-24 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-07-11 100% Analysis & design Planned: 2026-01-14 → 2026-04-19 Actual: 2026-02-19 → 2026-07-11
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-05-18 100% Business requirements Planned: 2026-01-14 → 2026-03-14 Actual: 2026-02-19 → 2026-05-18
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-11 100% Solution design Planned: 2026-02-20 → 2026-04-19 Actual: 2026-04-15 → 2026-07-11
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-07-11 100% Designs approved Planned: 2026-04-19 → 2026-04-19 Actual: 2026-07-11 → 2026-07-11 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-11-11 95% Build Planned: 2026-03-28 → 2026-08-07 Forecast: 2026-06-08 → 2026-11-11 Float: 0d
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-09-04 100% Release 1 Planned: 2026-03-28 → 2026-05-26 Actual: 2026-06-08 → 2026-09-04
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Release 2 Planned: 2026-05-04 → 2026-07-01 Actual: 2026-08-02 → 2026-10-26
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 85% Integrations Planned: 2026-06-09 → 2026-08-07 Forecast: 2026-06-09 → 2026-11-11 Float: 0d Drag to change its duration +96
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-11-11 0% Build complete Planned: 2026-08-07 → 2026-08-07 Forecast: 2026-11-11 → 2026-11-11 Float: 80d Drag to change its dates Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-12-21 0% Testing & acceptance Planned: 2026-07-16 → 2026-10-19 Forecast: 2026-10-30 → 2026-12-21 Float: 0d
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-01 0% System testing Planned: 2026-07-16 → 2026-09-12 Forecast: 2026-10-30 → 2026-12-01 Float: 0d Drag to change its dates +80
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-21 0% User acceptance testing Planned: 2026-08-21 → 2026-10-19 Forecast: 2026-11-19 → 2026-12-21 Float: 0d Drag to change its dates +63
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-21 0% Testing & acceptance complete Planned: 2026-10-19 → 2026-10-19 Forecast: 2026-12-21 → 2026-12-21 Float: 40d Drag to change its dates Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-30 0% Launch & handover Planned: 2026-09-27 → 2026-12-31 Forecast: 2026-12-09 → 2027-01-30 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-10 0% Training & change Planned: 2026-09-27 → 2026-11-24 Forecast: 2026-12-09 → 2027-01-10 Float: 0d Drag to change its dates +47
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-30 0% Go-live & handover Planned: 2026-11-03 → 2026-12-31 Forecast: 2026-12-29 → 2027-01-30 Float: 0d Drag to change its dates +30
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-30 0% Final handover Planned: 2026-12-31 → 2026-12-31 Forecast: 2027-01-30 → 2027-01-30 Float: 0d Drag to change its dates Final handover