PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Jeddah Branch & Qualification Centre

PRJ-2026-006 · Qualification & Training Sector · Strategic · WP-2024-006

Off track4ExecutionProject manager: Eng. Fahad T. Al-Sulami · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦39%⁩ / ⁦50%⁩
SPI · CPI
0.78 · 0.89
Spend
SAR 125.3M / SAR 286M
Estimate at completion
SAR 321.3M

Schedule

⁦11%⁩ behind⁦39%⁩

Planned to date ⁦50%⁩

Forecast finish: 2027-07-0429 Muharram 1449 AH · 95 days late

SPI0.78Schedule performance index · 0.78CPI0.89Cost performance index · 0.89

Health dimensions

Off track

Last update: 2026-10-2312 Jumada I 1448 AH · Up to date

Deliverables

⁦4⁩ of ⁦9⁩ due deliverables accepted on time (⁦44%⁩)

Next milestones

  • Build complete2027-01-113 Shaʻban 1448 AH
  • Testing & acceptance complete2027-04-2316 Dhuʻl-Qiʻdah 1448 AH
  • Final handover2027-06-3025 Muharram 1449 AH

Top risks

  • Ground-improvement costs up after the geotechnical survey16
  • Late building permits from the Jeddah municipality12

Open impediments

  • Foundation works stopped pending building permits · Escalated
  • Neighbouring entities objecting to the car-park entrance location · Open

Decisions and changes waiting

  • CR-2026-007 · Additional ground improvement after the geotechnical survey

Copilot summary

The scope holds 1 project with a budget of SAR 286M: 0 on track and 1 red or critical. Weighted progress is 39% against 50% planned, spend SAR 125.3M, and EAC SAR 321.3M (SAR 35.3M over).

1 project is more than a month behind baseline; the worst: Jeddah Branch & Qualification Centre (95 days).

Saudi Contractors Authority · prepared by Eng. Fahad T. Al-Sulami in MunjazInternal

Status: Off track ·Project page