Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
SCA-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2024-02-04⁩
Hijri
23 Rajab 1445 AH
ApprovedDMD-2026-006Jeddah Branch & Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Jeddah Branch & Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Fahad T. Al-Sulami

1The proposalAuto-filled

TitleAuto-filled
Jeddah Branch & Qualification Centre
Proposed byAuto-filled
Eng. Fahad T. Al-Sulami
DepartmentAuto-filled
Regional Qualification Centres Department
Submitted onAuto-filled
⁦2024-02-04⁩
Proposal numberAuto-filled
DMD-2026-006

2Justification

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

3Objectives

  1. A better contractor experience and service quality
  2. Build capability and innovation in the sector

Strategic objectives served

  • SO-3.3 — A better contractor experience and service quality
  • SO-2.1 — Build capability and innovation in the sector

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 286M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 205.9M
Supervision & consultingSAR 40.1M
Internal teamSAR 25.7M
Contingency reserve (5%)SAR 14.3M
TotalSAR 286M

6Initial risks

RiskLevelProposed response
Ground-improvement costs up after the geotechnical surveyHighTreated in the risk management plan
Late building permits from the Jeddah municipalityMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Fahad T. Al-SulamiDirector, Regional Qualification CentresSubmitted—⁦2024-02-04⁩ 14:59
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2024-02-06⁩ 12:09
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-02-08⁩ 13:16
4Portfolio manager reviewTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2024-02-13⁩ 14:23
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2024-02-15⁩ 14:35
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-02-19⁩ 10:37

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2024-02-06⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2024-02-08⁩

Portfolio manager review

Eng. Abdulrahman S. Al-Harbi

Approved⁦2024-02-13⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2024-02-15⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-02-19⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Fahad T. Al-Sulami on ⁦2024-02-04⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2024-02-06⁩ at ⁦12:09⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-02-08⁩ at ⁦13:16⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2024-02-13⁩ at ⁦14:23⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2024-02-15⁩ at ⁦14:35⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-02-19⁩ at ⁦10:37⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2024-02-25⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Fahad T. Al-Sulami

  2. V1Returned for edit⁦2024-02-04⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Fahad T. Al-Sulami

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close