Saudi Contractors AuthorityMunjaz11My actionsNotifications
PRJ-2026-006Off track4ExecutionConstruction

Jeddah Branch & Qualification Centre

Remove from watchlist

A new home for the Western & Southern branch in Jeddah with a qualification centre of 40 training and skills-test halls and contractor service desks.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 286M

Actual cost

SAR 125.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 321.3M

SAR +35.3M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Priority evaluation

Criteria, weights and the P1–P4 result

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
SCA-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2024-03-30⁩
Hijri
20 Ramadan 1445 AH
ApprovedPRJ-2026-006Jeddah Branch & Qualification Centre

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-006
Project
Jeddah Branch & Qualification Centre
Portfolio
Academy & Qualification Centres Portfolio
Sector
Qualification & Training Sector
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Fahad T. Al-Sulami

1The resultAuto-filled

Priority score

79 of 100

Class

P1

75–100

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the SCA strategy⁦20%⁩5.020.0
Value added to the contracting sector⁦12%⁩5.012.0
Financial return & sustainability⁦8%⁩5.08.0
Urgency⁦10%⁩4.79.3
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩2.44.5
Complexity⁦6%⁩2.73.4
Resource requirement⁦5%⁩3.32.1
Impact on contractors & beneficiaries⁦14%⁩5.014.0
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩3.32.9
Total⁦100%⁩—79

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Qualification Programmes & CapabilitySubmitted—⁦2024-03-30⁩ 09:24
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-03-31⁩ 13:28
3Portfolio manager reviewTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApproved—⁦2024-04-02⁩ 14:35
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-04-04⁩ 09:42

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2024-03-31⁩

Portfolio manager review

Eng. Abdulrahman S. Al-Harbi

Approved⁦2024-04-02⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-04-04⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2024-03-30⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-03-31⁩ at ⁦13:28⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2024-04-02⁩ at ⁦14:35⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-04-04⁩ at ⁦09:42⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2024-03-30⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.