Jeddah Branch & Qualification Centre Subtask Last item under this branch 2027-06-30 39% Jeddah Branch & Qualification Centre Planned: 2024-09-01 → 2027-03-31 Forecast: 2024-09-01 → 2027-06-30 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-02 100% Management & governance Planned: 2024-09-01 → 2025-03-14 Actual: 2024-09-01 → 2025-09-02
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-04-14 100% Project plan & baseline Planned: 2024-09-01 → 2024-12-29 Actual: 2024-09-01 → 2025-04-14
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-02 100% Monitoring & reporting Planned: 2024-11-15 → 2025-03-14 Actual: 2025-01-20 → 2025-09-02
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-02 100% Project plan approved Planned: 2025-03-14 → 2025-03-14 Actual: 2025-09-02 → 2025-09-02 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-06-10 100% Design & permits Planned: 2025-01-28 → 2025-08-11 Actual: 2025-06-09 → 2026-06-10
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-01-20 100% Detailed design Planned: 2025-01-28 → 2025-05-28 Actual: 2025-06-09 → 2026-01-20
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-10 100% Permits & approvals Planned: 2025-04-13 → 2025-08-11 Actual: 2025-10-28 → 2026-06-10
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-10 100% Designs approved Planned: 2025-08-11 → 2025-08-11 Actual: 2026-06-10 → 2026-06-10 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-11 55% Civil works Planned: 2025-06-27 → 2026-03-23 Forecast: 2025-09-09 → 2027-01-11 Float: 0d
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Site works & excavation Planned: 2025-06-27 → 2025-10-24 Actual: 2026-03-17 → 2026-10-26
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-08 66% Structure Planned: 2025-09-09 → 2026-01-07 Forecast: 2025-09-09 → 2026-12-08 Float: 0d Drag to change its duration +335
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-11 0% Finishes Planned: 2025-11-23 → 2026-03-23 Forecast: 2026-11-17 → 2027-01-11 Float: 0d Drag to change its dates +294
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-11 0% Build complete Planned: 2026-03-23 → 2026-03-23 Forecast: 2027-01-11 → 2027-01-11 Float: 170d Drag to change its dates Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-04-23 0% MEP works Planned: 2026-02-06 → 2026-11-02 Forecast: 2026-12-21 → 2027-04-23 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-14 0% Supply Planned: 2026-02-06 → 2026-06-05 Forecast: 2026-12-21 → 2027-02-14 Float: 0d Drag to change its dates +254
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-20 0% Installation Planned: 2026-04-21 → 2026-08-19 Forecast: 2027-01-24 → 2027-03-20 Float: 0d Drag to change its dates +213
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-23 0% Testing & commissioning Planned: 2026-07-05 → 2026-11-02 Forecast: 2027-02-27 → 2027-04-23 Float: 0d Drag to change its dates +172
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-23 0% Testing & acceptance complete Planned: 2026-11-02 → 2026-11-02 Forecast: 2027-04-23 → 2027-04-23 Float: 68d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-06-30 0% Handover Planned: 2026-09-18 → 2027-03-31 Forecast: 2027-04-02 → 2027-06-30 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-27 0% Provisional acceptance Planned: 2026-09-18 → 2027-01-15 Forecast: 2027-04-02 → 2027-05-27 Float: 0d Drag to change its dates +132
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-30 0% Final acceptance Planned: 2026-12-02 → 2027-03-31 Forecast: 2027-05-06 → 2027-06-30 Float: 0d Drag to change its dates +91
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-30 0% Final handover Planned: 2027-03-31 → 2027-03-31 Forecast: 2027-06-30 → 2027-06-30 Float: 0d Drag to change its dates Final handover