SCA Academy Campus, Riyadh Subtask Last item under this branch 2027-06-02 57% SCA Academy Campus, Riyadh Planned: 2024-02-04 → 2026-12-31 Forecast: 2024-02-04 → 2027-06-02 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-01-10 100% Management & governance Planned: 2024-02-04 → 2024-09-10 Actual: 2024-02-04 → 2025-01-10
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2024-09-01 100% Project plan & baseline Planned: 2024-02-04 → 2024-06-18 Actual: 2024-02-04 → 2024-09-01
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-01-10 100% Monitoring & reporting Planned: 2024-04-28 → 2024-09-10 Actual: 2024-06-14 → 2025-01-10
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-01-10 100% Project plan approved Planned: 2024-09-10 → 2024-09-10 Actual: 2025-01-10 → 2025-01-10 Project plan approved
2 Design & permits Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-09-29 100% Design & permits Planned: 2024-07-21 → 2025-02-25 Actual: 2024-10-23 → 2025-09-29
2.1 Detailed design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-21 100% Detailed design Planned: 2024-07-21 → 2024-12-03 Actual: 2024-10-23 → 2025-05-21
2.2 Permits & approvals Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-29 100% Permits & approvals Planned: 2024-10-14 → 2025-02-25 Actual: 2025-03-04 → 2025-09-29
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-29 100% Designs approved Planned: 2025-02-25 → 2025-02-25 Actual: 2025-09-29 → 2025-09-29 Designs approved
3 Civil works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Civil works Planned: 2025-01-06 → 2025-11-05 Actual: 2025-07-13 → 2026-10-26
3.1 Site works & excavation Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-08 100% Site works & excavation Planned: 2025-01-06 → 2025-05-21 Actual: 2025-07-13 → 2026-02-08
3.2 Structure Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-19 100% Structure Planned: 2025-03-31 → 2025-08-13 Actual: 2025-11-21 → 2026-06-19
3.3 Finishes Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Finishes Planned: 2025-06-23 → 2025-11-05 Actual: 2026-04-01 → 2026-10-26
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Build complete Planned: 2025-11-05 → 2025-11-05 Actual: 2026-10-26 → 2026-10-26 Build complete
4 MEP works Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-04-15 3% MEP works Planned: 2025-09-15 → 2026-07-16 Forecast: 2025-09-15 → 2027-04-15 Float: 0d
4.1 Supply Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-02-26 10% Supply Planned: 2025-09-15 → 2026-01-28 Forecast: 2025-09-15 → 2027-02-26 Float: 0d Drag to change its duration +394
4.2 Installation Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-03-22 0% Installation Planned: 2025-12-09 → 2026-04-22 Forecast: 2027-02-12 → 2027-03-22 Float: 0d Drag to change its dates +334
4.3 Testing & commissioning Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-15 0% Testing & commissioning Planned: 2026-03-03 → 2026-07-16 Forecast: 2027-03-08 → 2027-04-15 Float: 0d Drag to change its dates +273
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-04-15 0% Testing & acceptance complete Planned: 2026-07-16 → 2026-07-16 Forecast: 2027-04-15 → 2027-04-15 Float: 48d Drag to change its dates Testing & acceptance complete
5 Handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-06-02 0% Handover Planned: 2026-05-26 → 2026-12-31 Forecast: 2027-04-01 → 2027-06-02 Float: 0d
5.1 Provisional acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-05-09 0% Provisional acceptance Planned: 2026-05-26 → 2026-10-08 Forecast: 2027-04-01 → 2027-05-09 Float: 0d Drag to change its dates +213
5.2 Final acceptance Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-02 0% Final acceptance Planned: 2026-08-18 → 2026-12-31 Forecast: 2027-04-25 → 2027-06-02 Float: 0d Drag to change its dates +153
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-06-02 0% Final handover Planned: 2026-12-31 → 2026-12-31 Forecast: 2027-06-02 → 2027-06-02 Float: 0d Drag to change its dates Final handover