PRJ-2026-017At risk5ClosureWaterfall

Correspondence & Document Management System (DMS)

Add to watchlist

Automated correspondence, document management and e-archiving, linked to the government communications network.

Budget (BAC)

SAR 14.2M

Actual cost

SAR 13.5M

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 14.2M

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Saudi Contractors AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
SCA-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-01-26⁩
Hijri
26 Rajab 1446 AH
ApprovedMTG-KO-017Kick-off — Correspondence & Document Management System (DMS)

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System (DMS)
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation Sector
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Correspondence & Document Management System (DMS)
Date and timeAuto-filled
⁦2025-01-26⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Dana S. Al-Saleh

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Sarah A. Al-QarniHead, Corporate Support Sector
Munirah A. Al-KhalidiDirector General, Finance & Procurement
Dana S. Al-SalehDirector, Enterprise Systems & Integration
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Sarah A. Al-QarniProject sponsorSponsors the project, decides escalations and material changes
Munirah A. Al-KhalidiProject ownerApproves the requirements and accepts the deliverables
Dana S. Al-SalehProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedDana S. Al-Saleh⁦2025-06-07⁩Done
Designs approvedDana S. Al-Saleh⁦2025-09-21⁩Done
Build completeDana S. Al-Saleh⁦2026-03-01⁩Done
Testing & acceptance completeDana S. Al-Saleh⁦2026-06-15⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Control Board: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-04-28⁩
Start confirmed
Sarah A. Al-Qarni · ⁦2025-01-27⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-01-27⁩ 13:40
2Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-01-28⁩ 11:44
3Chair’s approval (sponsor)Technical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-01-28⁩ 12:30

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-01-28⁩

Chair’s approval (sponsor)

Sarah A. Al-Qarni

Approved⁦2025-01-28⁩

Issued from Munjaz — Saudi Contractors Authority · ⁦2026-10-28⁩Form SCA-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2025-01-27⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-01-28⁩ at ⁦11:44⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-01-28⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-01-26⁩

    The minutes as taken

    Dana S. Al-Saleh

Only one version so far.